DRRRP Awarded Dl DL Stage 01

RR/RDA/SP/16/25/02

Karana junction south pahalawela palanoya road (From near Pahalalanda post office junction to Karanagama)

AmparaEastern ProvinceAmparaDivisional Secretariat-ContractorLKR 171,722,366.66Contract Sum0 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-06-22
Completed
Scheduled Completion
–
Pending
Anticipated Completion Date
2025-11-15
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceEastern Province
DistrictAmpara
DS Division-
GN Division-
Electorate-
PD RegionEastern Province (Akkaraipattu)
CE RegionAmpara
EE DivisionAmpara
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Ampara