DRRRP Awarded Dl DL Stage 03

RR/GA/21/25/CC/12

Girithale janapadaya pasal mawatha carpet kara ithiri kotasa wana D.G. Jayasiri mahathage niwasa asala sita Akkara 15 handiya Jhon Raja mahathage niwasa dakwa margaya

PolonnaruwaNorth Central ProvinceHabaranaDivisional Secretariat-ContractorLKR 42,689,736.99Contract Sum0 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-09-17
Completed
Scheduled Completion
–
Pending
Anticipated Completion Date
2026-01-31
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Central Province
DistrictPolonnaruwa
DS Division-
GN Division-
Electorate-
PD RegionNorth Central Province
CE RegionPolonnaruwa
EE DivisionHabarana
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Hingurakgoda