DRRRP Awarded Dl DL Stage 02

RR/RDA/25/24/12

Siyabalagahayata Junction to Blue Mountain Housing Complex Road

RatnapuraSabaragamuwa ProvinceRatnapuraDivisional Secretariat-ContractorLKR 23,571,917.19Contract Sum37 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-09-04
Completed
Scheduled Completion
2025-10-10
Completed
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
DS Division-
GN Division-
Electorate-
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionRatnapura
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Kuruvita