DRRRP Awarded Dl DL Stage 02

RR/RDA/25/24/09

From Koralegama to Labuwalwaththa Road (From Mr.Pushpananda House)

RatnapuraSabaragamuwa ProvincePelmadullaDivisional Secretariat-ContractorLKR 33,251,409.79Contract Sum68 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-09-09
Completed
Scheduled Completion
2025-11-15
Completed
Anticipated Completion Date
2025-11-05
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
DS Division-
GN Division-
Electorate-
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionPelmadulla
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Kahawatta