DRRRP Awarded Dl DL Stage 02

RR/RDA/25/25/18

Concreting Beragala Army Camp to Beragala 3way Junction VIA Niyadagala

KegalleSabaragamuwa ProvinceKegalleDivisional Secretariat-ContractorLKR 34,687,905.11Contract Sum67 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-08-26
Completed
Scheduled Completion
2025-10-31
Completed
Anticipated Completion Date
2025-10-25
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictKegalle
DS Division-
GN Division-
Electorate-
PD RegionSabaragamuwa Province
CE RegionKegalle
EE DivisionKegalle
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Kegalle