DRRRP Awarded Dl DL Stage 01

RR/RDA/25/08/01

Kajjuhena Margaya Sanwardanaya Kirima (Kajjuhena Handiya Sita Alikavila Budu Madura Dakwa ) I adiyara

MataraSouthern ProvinceDeniyayaDivisional Secretariat-ContractorLKR 78,061,393.44Contract Sum117 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-06-21
Completed
Scheduled Completion
2025-10-15
Completed
Anticipated Completion Date
2026-01-31
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSouthern Province
DistrictMatara
DS Division-
GN Division-
Electorate-
PD RegionSouthern Province
CE RegionMatara
EE DivisionDeniyaya
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Athuraliya