DRRRP Awarded Dl DL Stage 03

RR/RDA/03/25/13

Morapitiya Aluth Mawatha to 1st mile post via Rankoth lane

KalutaraWestern ProvinceAgalawattaDivisional Secretariat-ContractorLKR 38,713,954.65Contract Sum0 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-09-16
Completed
Scheduled Completion
–
Pending
Anticipated Completion Date
2026-02-28
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceWestern Province
DistrictKalutara
DS Division-
GN Division-
Electorate-
PD RegionWestern Province
CE RegionKalutara
EE DivisionAgalawatta
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Palindanura