DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 3 awarded projects

2026-11-04
11:41:37Live2026-11-04
0 / 3Advance Pendingpending advance projects / total projects
0 / 3IPC Pendingpending IPC projects / total projects
1 / 3Advance Paidadvance paid projects / total projects
0 / 3IPCs PaidIPC paid projects / total projects
7.8 Mn

7.84 Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

7.8 Mn

7.84 Mn

Total Paid (excl. VAT)

9.2 Mn

9.25 Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

9.2 Mn

9.25 Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

1.4%

1.4%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

8.5%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · EE: Hanguranketha · EE Office

155Projects31,163.5Contract Mn
Reset
Hanguranketha 3 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency147.89.219% of contract—117.8———100.0%16.4%
DC - Roads00.0——————————
DC - Slope2512.3————————0.0%0.0%
PD(CP) - Slope00.0——————————
Hanguranketha3560.19.22% of contract0.0117.8000.033.3%1.4%
Emergency1 project47.8Mn
19% paid9.2 Mn
Pending—
Planned Fin100.0%
Actual Fin16.4%
Advance & IPC
Advance paid1 proj · 7.8 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Roads0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope2 projects512.3Mn
0% paid0.0 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Hanguranketha3 projects560.1Mn
2% paid9.2 Mn
Pending0.0Mn
Planned Fin33.3%
Actual Fin1.4%

Avg Physical Progress per Province · EE: Hanguranketha

Project-wise Financials · EE: Hanguranketha (3 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Hanguranketha (Mn · incl. VAT)

Hanguranketha Division · EE: Hanguranketha (Mn · incl. VAT)

Nuwara Eliya District Summary (Mn · incl. VAT)

District baseline — overall all categories (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:3 awarded · EE: Hanguranketha
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 3 projects (filtered from 171)

1–3/3 (filtered from 171)

Filter financial register

3 matching projects1 active

ActiveProgress 100–100%
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
1RDA/DRP/SAB/RAT/PEL/19
Rehabilitation / Improvement and Retaining wall Construction of (Galle - Deniya…
Solinro Builders
95,082,996.5816,436,817.5619,395,444.72——38,373,715.8845,280,984.74——54,810,533.44—
64.68Mn
68%
On Track
64.68Mn
68%
2RDA/DRP/NCP/POL/POL/08
Rehabilitation / Improvement and Reconstruction of 31/1 Culvert, Construction Of…
Sawsiri Construction
17,459,311.37————9,866,233.2111,642,155.19——9,866,233.21—
11.64Mn
66.7%
On Track
11.64Mn
66.7%
3RDA/DRP/SP/GAL/GAL/02
Rehabilitation of Gabbion Walls along Galle - Deniyaya - Madampe Road (from7+700…
Ceylon Construction Industry Development…
8,991,852.34————————————
Total121,534,160.2916,436,817.5619,395,444.72——48,239,949.0956,923,139.93——64,676,766.65—
76.32Mn
62.8%
76.32Mn
62.8%