DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 24 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-04 10:30Live
Graphs reflect current view:24 awarded · Central Province · Nuwara Eliya

Portfolio Breakdown · Central Province · Nuwara Eliya · District

57Awarded131Total
Nuwara Eliya 24 awarded of 56 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp ex-VATPlanned %Actual %
Emergency10100100%2,032.01,668.31,329.5294.818% of contract89.4%44.0%
DC - Roads1981142%11,271.25,116.614.4—0.5%5.8%
DC - Slope2361726%8,208.01,731.6——0.0%0.0%
PD(CP) - Slope4040%102.30.0————
Nuwara Eliya56243243%21,613.58,516.51,344.0294.83% of contract37.4%20.3%

Avg Physical Progress per EE Division · Central Province · Nuwara Eliya

Portfolio Timeline· 13 scheduled projects · Central Province · Nuwara Eliya Toggle
Portfolio · Awarded Works

Awarded Projects

24 projects

24/24

Filter awarded works

24 matching projects

Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/CEN/NUE/HAN/57
Rehabilitation / Improvement of Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )
30%
47,755,538.9644,694,533.62Awarded
RDA/DRP/CEN/NUE/NUE/60R
Rehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (A005) (40+750 - 42+850)
10%
336,313,078.73338,287,510.33Awarded
RDA/DRP/CEN/NUE/NUE/66
Rehabilitation / Improvement of Nuwara Eliya Town Road (0+000 - 1+695 ) (0+000 - 0+240 )
69%
161,841,095.70205,630,098.81Awarded
RDA/DRP/CEN/NUE/NUE/67
Rehabilitation / Improvement of Harangala - Kalapitiya - Kumbaloluwa Road (10+480 km - 17+140 km)
78%
239,417,811.34302,933,613.60Awarded
RDA/DRP/CEN/NUE/NUE/68
Rehabilitation / Improvement of Thawalanthenna Thalawakelle Road (0+000 - 8+000) & (10+000 - 33+200)
40%
213,999,600.01296,813,201.99Awarded
RDA/DRP/CEN/NUE/NUE/69
Rehabilitation / Improvement of Ulapane Pussallawa Road (6+440 - 15+950)
56%
266,045,892.19365,868,062.33Awarded
RDA/DRP/CEN/NUE/NUE/86
Rehabilitation / Improvement of Approch road to R'way station (Watagoda/ Thalawakele) Road
20%
33,765,626.8641,996,395.31Awarded
RDA/DRP/CEN/NUE/NUR/97
Rehabilitation/Improvement of Nawalapitiya Ginigathena Road (B-319)(7+200-12+200)
62%
93,758,217.76104,490,700.33Awarded
RDA/DRP/CEN/NUE/NUR/98
Rehabilitation/Improvement Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Hrangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700)
44%
188,617,394.68222,691,835.72Awarded
RDA/DRP/CEN/NUE/NUR/101
Rehabilitation/Improvement of Hatton Maskeliya Delhouse Road (B-149) (0+000-31+970)
31%
86,746,198.17108,611,538.67Awarded
RDA/DC/DRP/CP/NE/NRW/02
REHABILITATION/ IMPROVEMENT OF APPROCH ROAD TO LAXAPANA POWER HOUSE ROAD CH 6+100 - 12+000
9%
374,859,845.10348,620,000.00Awarded
RDA/DC/DRP/CP/NE/NE/04
REHABILITAION/ IMPROVEMENTS OF LADY MACALUMS DRIVE ROAD (2+850 - 5+600KM)
1%
636,338,397.00560,630,000.00Awarded
RDA/DC/DRP/CP/NE/NRW/03
REHABILITATION/ IMPROVEMENT TO ROZELLA RAILWAY STATION ROAD (0+000 - 3+300) KM AND WATAWALA RAILWAY STATION ROAD (0+000 - 1+850) KM
19%
604,298,969.28509,310,000.00Awarded
RDA/DC/DRP/CP/NE/NE/14
Rehabilitation/ Improvement of Lady Macalums Drive (0+000 - 2+700)
0%
711,929,618.35575,100,000.00Awarded
RDA/DC/DRP/CP/NE/NE/05
Rehabilitation/ Improvement of Blackpool Ambewela Pattipola Hortan Plains (5+200 - 12+000)
0%
791,681,996.67612,060,000.00Awarded
RDA/DC/DRP/CP/NE/NE/01
Rehabilitation/ Improvement of Blackpool Ambewela Pattipola Hortan Plains (12+500 - 18+000)
0%
744,680,423.80605,620,000.00Awarded
RDA/DC/DRP/CP/NE/NE/09
Rehabilitation/ Improvement to Blackpool Ambewela Pattipola Hortan Plains ( 19+000 - 23+000)
0%
607,139,242.74487,070,000.00Awarded
RDA/DC/DRP/CP/NE/NE/07
Rehabilitation/ Improvement to Gomburuoya - Balapokuna Road 0+000-8+500Without 5+250-5+450 & 6+900-7+150
0%
645,688,890.82521,587,977.73Awarded
RDA/DC/DRP/SLOPE/CP/NUE/NUE/PACKAGE-31
REHABILITATION OF SELECTED ROADSECTIONS ON PERADENIYA-BADULLA-CHENKALADI ROAD(44TH KM) AND SLOPE FAILURES DUE TO DITWAH CYCLONE
0%
376,649,403.13320,000,000.00Awarded
RDA/DC/DRP/SLOPE/CP/NUE/NOR/PACKAGE 33
MITIGATION FOR FAILURE LOCATIONS ALONG NORTON MASKELIYA ROAD (B328) (7+020 7+510) AND SLOPE FAILURES DUE TO "DITWAH" CYCLONE -PACKAGE 33
0%
220,338,719.68216,000,000.00Awarded
RDA/DC/DRP/SLOPE/CP/NUE/NUE/PACKAGE-03
MITIGATION OF SLOPE FAILURE LOCATIONS ALONG GOMBURU OYA-BALAPOKUNA ROAD (B582) 6+900 KM-7+100 KM DUE TO DITWAH CYCLONE - PACKAGE 03
0%
357,941,434.50262,030,000.00Awarded
RDA/DC/DRP/SLOPE/CP/NUE/HAN/PACKAGE 26E
REHABILITATION OF SELECTED ROAD SECTIONS ON THENNEKUMBURA RIKILLAGASKADA RAGALA ROAD (B413) (50+100-70+950 ) AND SLOPE FAILURES DUE TO "DITWAH" CYCLONE-PACKAGE 26E
0%
332,123,863.50322,400,000.00Awarded
RDA/DC/DRP/SLOPE/CP/NUE/HAN/PACKAGE 26C
MITIGATION FOR FAILURE LOCATIONS ALONG THENNEKUMBURA RIKILLAGASKADA RAGALA ROAD (B413) (48/11 - 48/12) & (67/10 - 67 km) DUE TO "DITWAH" CYCLONE-PACKAGE 26C
0%
180,175,018.14159,300,000.00Awarded
RDA/DC/DRP/SLOPE/CP/NUE/NOR/PACKAGE 28A
MITIGATION FOR FAILURE LOCATIONS ALONG AWISSAWELLA HATTON NUWARAELIYA ROAD (A007) (41+800 & 42+960) DUE TO "DITWAH" CYCLONE - PACKAGE 28A
0%
264,416,347.31232,200,000.00Awarded
Showing 1–24 of 24
Per page:
Source: DRRRP • 56 projects • Data updated 2026-11-04 10:30 • 10:48:37