DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 24 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-02 15:53Live
Graphs reflect current view:24 awarded · Central Province · Nuwara Eliya
42.9% awarded
0
Awarded
56 total projects in portfolio
Awarded projects24
RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )RDA/DRP/CEN/NUE/NUE/60RPeradeniya Badulla Chenkaladi Road (A005)RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)RDA/DRP/CEN/NUE/NUE/67Harangala - Kalapitiya - Kumbaloluwa Road (B148)RDA/DRP/CEN/NUE/NUE/68Thawalanthenna Thalawakelle Road (B412)RDA/DRP/CEN/NUE/NUE/69Ulapane Pussallawa Road (B431)RDA/DRP/CEN/NUE/NUE/86Approch road to R'way station (Watagoda) RoadRDA/DRP/CEN/NUE/NUR/97Nawalapitiya Ginigathena Road (B-319)RDA/DRP/CEN/NUE/NUR/98Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Harangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700)RDA/DRP/CEN/NUE/NUR/101Hatton Maskeliya Delhouse Road (B-149)RDA/DC/DRP/CP/NE/NRW/02REHABILITATION/ IMPROVEMENT OF APPROACH ROAD TO LAXAPANA POWER HOUSE ROAD CH (6+100 TO 12+000) KMRDA/DC/DRP/CP/NE/NE/04LADY MACALUMS DRIVE ROADRDA/DC/DRP/CP/NE/NRW/03RDA/DC/DRP/CP/NE/NE/14RDA/DC/DRP/CP/NE/NE/05
+9 more…
Click to filter the awarded table
8,516.5M
8,516.5 Mn
Contract Value
Awarded projects24
RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )RDA/DRP/CEN/NUE/NUE/60RPeradeniya Badulla Chenkaladi Road (A005)RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)RDA/DRP/CEN/NUE/NUE/67Harangala - Kalapitiya - Kumbaloluwa Road (B148)RDA/DRP/CEN/NUE/NUE/68Thawalanthenna Thalawakelle Road (B412)RDA/DRP/CEN/NUE/NUE/69Ulapane Pussallawa Road (B431)RDA/DRP/CEN/NUE/NUE/86Approch road to R'way station (Watagoda) RoadRDA/DRP/CEN/NUE/NUR/97Nawalapitiya Ginigathena Road (B-319)RDA/DRP/CEN/NUE/NUR/98Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Harangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700)RDA/DRP/CEN/NUE/NUR/101Hatton Maskeliya Delhouse Road (B-149)RDA/DC/DRP/CP/NE/NRW/02REHABILITATION/ IMPROVEMENT OF APPROACH ROAD TO LAXAPANA POWER HOUSE ROAD CH (6+100 TO 12+000) KMRDA/DC/DRP/CP/NE/NE/04LADY MACALUMS DRIVE ROADRDA/DC/DRP/CP/NE/NRW/03RDA/DC/DRP/CP/NE/NE/14RDA/DC/DRP/CP/NE/NE/05
+9 more…
Click to filter the awarded table
Avg
31.3%
13
works in progress
0 completed
Avg Progress
Awarded projects24
RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )RDA/DRP/CEN/NUE/NUE/60RPeradeniya Badulla Chenkaladi Road (A005)RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)RDA/DRP/CEN/NUE/NUE/67Harangala - Kalapitiya - Kumbaloluwa Road (B148)RDA/DRP/CEN/NUE/NUE/68Thawalanthenna Thalawakelle Road (B412)RDA/DRP/CEN/NUE/NUE/69Ulapane Pussallawa Road (B431)RDA/DRP/CEN/NUE/NUE/86Approch road to R'way station (Watagoda) RoadRDA/DRP/CEN/NUE/NUR/97Nawalapitiya Ginigathena Road (B-319)RDA/DRP/CEN/NUE/NUR/98Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Harangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700)RDA/DRP/CEN/NUE/NUR/101Hatton Maskeliya Delhouse Road (B-149)RDA/DC/DRP/CP/NE/NRW/02REHABILITATION/ IMPROVEMENT OF APPROACH ROAD TO LAXAPANA POWER HOUSE ROAD CH (6+100 TO 12+000) KMRDA/DC/DRP/CP/NE/NE/04LADY MACALUMS DRIVE ROADRDA/DC/DRP/CP/NE/NRW/03RDA/DC/DRP/CP/NE/NE/14RDA/DC/DRP/CP/NE/NE/05
+9 more…
Click to filter the awarded table
347.9M
347.9 Mn
Total Expenditure (incl. VAT)
Awarded projects24
RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )RDA/DRP/CEN/NUE/NUE/60RPeradeniya Badulla Chenkaladi Road (A005)RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)RDA/DRP/CEN/NUE/NUE/67Harangala - Kalapitiya - Kumbaloluwa Road (B148)RDA/DRP/CEN/NUE/NUE/68Thawalanthenna Thalawakelle Road (B412)RDA/DRP/CEN/NUE/NUE/69Ulapane Pussallawa Road (B431)RDA/DRP/CEN/NUE/NUE/86Approch road to R'way station (Watagoda) RoadRDA/DRP/CEN/NUE/NUR/97Nawalapitiya Ginigathena Road (B-319)RDA/DRP/CEN/NUE/NUR/98Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Harangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700)RDA/DRP/CEN/NUE/NUR/101Hatton Maskeliya Delhouse Road (B-149)RDA/DC/DRP/CP/NE/NRW/02REHABILITATION/ IMPROVEMENT OF APPROACH ROAD TO LAXAPANA POWER HOUSE ROAD CH (6+100 TO 12+000) KMRDA/DC/DRP/CP/NE/NE/04LADY MACALUMS DRIVE ROADRDA/DC/DRP/CP/NE/NRW/03RDA/DC/DRP/CP/NE/NE/14RDA/DC/DRP/CP/NE/NE/05
+9 more…
Click to filter the awarded table
16.7%
0
On Progress
4 / 24 awarded
On Progress (incl. completed)4
RDA/DRP/CEN/NUE/NUE/60RPeradeniya Badulla Chenkaladi Road (A005)RDA/DC/DRP/CP/NE/NRW/02REHABILITATION/ IMPROVEMENT OF APPROACH ROAD TO LAXAPANA POWER HOUSE ROAD CH (6+100 TO 12+000) KMRDA/DC/DRP/CP/NE/NE/04LADY MACALUMS DRIVE ROADRDA/DC/DRP/CP/NE/NRW/03
Click to filter the awarded table
0%
0
Delay
0 / 24 awarded
Delay0
No projects
Click to filter the awarded table
37.5%
0
Critical Delay
9 / 24 awarded
Critical Delay9
RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)RDA/DRP/CEN/NUE/NUE/67Harangala - Kalapitiya - Kumbaloluwa Road (B148)RDA/DRP/CEN/NUE/NUE/68Thawalanthenna Thalawakelle Road (B412)RDA/DRP/CEN/NUE/NUE/69Ulapane Pussallawa Road (B431)RDA/DRP/CEN/NUE/NUE/86Approch road to R'way station (Watagoda) RoadRDA/DRP/CEN/NUE/NUR/97Nawalapitiya Ginigathena Road (B-319)RDA/DRP/CEN/NUE/NUR/98Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Harangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700)RDA/DRP/CEN/NUE/NUR/101Hatton Maskeliya Delhouse Road (B-149)
Click to filter the awarded table
0%
0
Completed
0 / 24 awarded
Completed0
No projects
Click to filter the awarded table
Portfolio Breakdown · Central Province · Nuwara Eliya · District
Avg Physical Progress per EE Division · Central Province · Nuwara Eliya
At-Risk Projects · Central Province · Nuwara Eliya
- RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)Delay96 Days in Delay · 69%
- RDA/DRP/CEN/NUE/NUE/86Approch road to R'way station (Watagoda) RoadDelay55 Days in Delay · 20%
- RDA/DRP/CEN/NUE/NUR/97Nawalapitiya Ginigathena Road (B-319)Delay50 Days in Delay · 62%
- RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )Delay7 Days in Delay · 30%
- RDA/DRP/CEN/NUE/NUE/67Harangala - Kalapitiya - Kumbaloluwa Road (B148)Delay5 Days in Delay · 78%
- RDA/DRP/CEN/NUE/NUE/68Thawalanthenna Thalawakelle Road (B412)Delay5 Days in Delay · 40%
- RDA/DRP/CEN/NUE/NUE/69Ulapane Pussallawa Road (B431)Delay5 Days in Delay · 56%
Portfolio Timeline· 13 scheduled projects · Central Province · Nuwara Eliya Toggle
2026-05-02 today2028-03-15
Portfolio · Awarded Works
Awarded Projects
24 projects
Filter awarded works
24 matching projects
| Contract No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|
| RDA/DRP/CEN/NUE/HAN/57 | Rehabilitation / Improvement of Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 ) | 30% | 47,755,538.96 | 44,694,533.62 | Awarded |
| RDA/DRP/CEN/NUE/NUE/60R | Rehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (A005) (40+750 - 42+850) | 10% | 336,313,078.73 | 338,287,510.33 | Awarded |
| RDA/DRP/CEN/NUE/NUE/66 | Rehabilitation / Improvement of Nuwara Eliya Town Road (0+000 - 1+695 ) (0+000 - 0+240 ) | 69% | 161,841,095.70 | 205,630,098.81 | Awarded |
| RDA/DRP/CEN/NUE/NUE/67 | Rehabilitation / Improvement of Harangala - Kalapitiya - Kumbaloluwa Road (10+480 km - 17+140 km) | 78% | 239,417,811.34 | 302,933,613.60 | Awarded |
| RDA/DRP/CEN/NUE/NUE/68 | Rehabilitation / Improvement of Thawalanthenna Thalawakelle Road (0+000 - 8+000) & (10+000 - 33+200) | 40% | 213,999,600.01 | 296,813,201.99 | Awarded |
| RDA/DRP/CEN/NUE/NUE/69 | Rehabilitation / Improvement of Ulapane Pussallawa Road (6+440 - 15+950) | 56% | 266,045,892.19 | 365,868,062.33 | Awarded |
| RDA/DRP/CEN/NUE/NUE/86 | Rehabilitation / Improvement of Approch road to R'way station (Watagoda/ Thalawakele) Road | 20% | 33,765,626.86 | 41,996,395.31 | Awarded |
| RDA/DRP/CEN/NUE/NUR/97 | Rehabilitation/Improvement of Nawalapitiya Ginigathena Road (B-319)(7+200-12+200) | 62% | 93,758,217.76 | 104,490,700.33 | Awarded |
| RDA/DRP/CEN/NUE/NUR/98 | Rehabilitation/Improvement Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Hrangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700) | 44% | 188,617,394.68 | 222,691,835.72 | Awarded |
| RDA/DRP/CEN/NUE/NUR/101 | Rehabilitation/Improvement of Hatton Maskeliya Delhouse Road (B-149) (0+000-31+970) | 31% | 86,746,198.17 | 108,611,538.67 | Awarded |
| RDA/DC/DRP/CP/NE/NRW/02 | REHABILITATION/ IMPROVEMENT OF APPROCH ROAD TO LAXAPANA POWER HOUSE ROAD CH 6+100 - 12+000 | 9% | 374,859,845.10 | 348,620,000.00 | Awarded |
| RDA/DC/DRP/CP/NE/NE/04 | REHABILITAION/ IMPROVEMENTS OF LADY MACALUMS DRIVE ROAD (2+850 - 5+600KM) | 1% | 636,338,397.00 | 560,630,000.00 | Awarded |
| RDA/DC/DRP/CP/NE/NRW/03 | REHABILITATION/ IMPROVEMENT TO ROZELLA RAILWAY STATION ROAD (0+000 - 3+300) KM AND WATAWALA RAILWAY STATION ROAD (0+000 - 1+850) KM | 19% | 604,298,969.28 | 509,310,000.00 | Awarded |
| RDA/DC/DRP/CP/NE/NE/14 | Rehabilitation/ Improvement of Lady Macalums Drive (0+000 - 2+700) | 0% | 711,929,618.35 | 575,100,000.00 | Awarded |
| RDA/DC/DRP/CP/NE/NE/05 | Rehabilitation/ Improvement of Blackpool Ambewela Pattipola Hortan Plains (5+200 - 12+000) | 0% | 791,681,996.67 | 612,060,000.00 | Awarded |
| RDA/DC/DRP/CP/NE/NE/01 | Rehabilitation/ Improvement of Blackpool Ambewela Pattipola Hortan Plains (12+500 - 18+000) | 0% | 744,680,423.80 | 605,620,000.00 | Awarded |
| RDA/DC/DRP/CP/NE/NE/09 | Rehabilitation/ Improvement to Blackpool Ambewela Pattipola Hortan Plains ( 19+000 - 23+000) | 0% | 607,139,242.74 | 487,070,000.00 | Awarded |
| RDA/DC/DRP/CP/NE/NE/07 | Rehabilitation/ Improvement to Gomburuoya - Balapokuna Road 0+000-8+500Without 5+250-5+450 & 6+900-7+150 | 0% | 645,688,890.82 | 521,587,977.73 | Awarded |
| RDA/DC/DRP/SLOPE/CP/NUE/NUE/PACKAGE-31 | REHABILITATION OF SELECTED ROADSECTIONS ON PERADENIYA-BADULLA-CHENKALADI ROAD(44TH KM) AND SLOPE FAILURES DUE TO DITWAH CYCLONE | 0% | 376,649,403.13 | 320,000,000.00 | Awarded |
| RDA/DC/DRP/SLOPE/CP/NUE/NOR/PACKAGE 33 | MITIGATION FOR FAILURE LOCATIONS ALONG NORTON MASKELIYA ROAD (B328) (7+020 7+510) AND SLOPE FAILURES DUE TO "DITWAH" CYCLONE -PACKAGE 33 | 0% | 220,338,719.68 | 216,000,000.00 | Awarded |
| RDA/DC/DRP/SLOPE/CP/NUE/NUE/PACKAGE-03 | MITIGATION OF SLOPE FAILURE LOCATIONS ALONG GOMBURU OYA-BALAPOKUNA ROAD (B582) 6+900 KM-7+100 KM DUE TO DITWAH CYCLONE - PACKAGE 03 | 0% | 357,941,434.50 | 262,030,000.00 | Awarded |
| RDA/DC/DRP/SLOPE/CP/NUE/HAN/PACKAGE 26E | REHABILITATION OF SELECTED ROAD SECTIONS ON THENNEKUMBURA RIKILLAGASKADA RAGALA ROAD (B413) (50+100-70+950 ) AND SLOPE FAILURES DUE TO "DITWAH" CYCLONE-PACKAGE 26E | 0% | 332,123,863.50 | 322,400,000.00 | Awarded |
| RDA/DC/DRP/SLOPE/CP/NUE/HAN/PACKAGE 26C | MITIGATION FOR FAILURE LOCATIONS ALONG THENNEKUMBURA RIKILLAGASKADA RAGALA ROAD (B413) (48/11 - 48/12) & (67/10 - 67 km) DUE TO "DITWAH" CYCLONE-PACKAGE 26C | 0% | 180,175,018.14 | 159,300,000.00 | Awarded |
| RDA/DC/DRP/SLOPE/CP/NUE/NOR/PACKAGE 28A | MITIGATION FOR FAILURE LOCATIONS ALONG AWISSAWELLA HATTON NUWARAELIYA ROAD (A007) (41+800 & 42+960) DUE TO "DITWAH" CYCLONE - PACKAGE 28A | 0% | 264,416,347.31 | 232,200,000.00 | Awarded |
Showing 1–24 of 24
Source: DRRRP • 56 projects • Data updated 2026-11-02 15:53 • 09:57:56 System live • Sri Lanka • 1 districts