DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 5 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 15:53Live
Graphs reflect current view:5 awarded · EE: Polonnaruwa
20%

0

On Progress

1 / 5 awarded

20%

0

Delay

1 / 5 awarded

20%

0

Completed

1 / 5 awarded

Portfolio Breakdown · EE: Polonnaruwa · EE Office

155Awarded237Total
Polonnaruwa 5 awarded of 5 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Emergency550100%280.3235.4235.464.727% of contract100.0%68.2%
DC - Roads0000%0.00.0————
DC - Slope0000%0.00.0————
PD(CP) - Slope0000%0.00.0————
Polonnaruwa550100%280.3235.4235.464.727% of contract100.0%68.2%

Avg Physical Progress per EE Division · EE: Polonnaruwa

Portfolio Timeline· 5 scheduled projects · EE: Polonnaruwa Toggle
Portfolio · Awarded Works

Awarded Projects

3 projects

3/3 (filtered)

Filter awarded works

3 matching projects1 active

ActiveCritical Delay
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/NCP/POL/POL/09
Rehabilitation / Improvement and Reconstruction of Culvert No. 104/2, Construction of New Drainage At 83km, and Concrete Hard Shoulder at 83 Km on Maradankadawala - Habarana - Thirikkondiyadumadu Road (A-11) (82+110 - 82+860 (B/S)
56%
94,457,054.66119,605,688.26Awarded
RDA/DRP/NCP/POL/POL/10
Rehabilitation / Improvement and Construction of New Drainage At 65-78km on Maradankadawala Habarana Thirikkondiyadumadu Road (A011)Road
55%
29,767,050.5333,973,362.07Awarded
RDA/DRP/NCP/POL/POL/11
Rehabilitation / Improvement and Construction of New Drainage on Polonnaruwa-Thambala -Sungawila -Somawathiya- Road
40%
44,474,738.8257,461,708.21Awarded
Showing 1–3 of 3
Per page:
Source: DRRRP • 5 projects • Data updated 2026-11-02 15:53 • 09:53:03