Comprehensive overview of 1 infrastructure projects under the Disaster Rehabilitation Programme. · Hanguranketha EE

Updated 2026-09-24 15:27Live
Graphs reflect current view: 1 awarded · Hanguranketha EE · EE: Hanguranketha

Portfolio at a Glance

1 awarded works · Hanguranketha EE · EE: Hanguranketha

2026-09-24 15:27
100% awarded

0

Awarded

1 total projects in portfolio

47.8M

47.8 Mn

Contract Value

Spent 0% Remaining 100%
Avg
10%

1

works in progress

0 completed

Avg Progress

0.0M

0.0 Mn

Total Expenditure (excl. VAT)

0% of contract excl. VAT
0%

0

Kick Off Pending

0 / 1 awarded

0%

0

Mobilization Pending

0 / 1 awarded

0%

0

Works Not Started

0 / 1 awarded

0%

0

Completed

0 / 1 awarded

Portfolio Breakdown · Hanguranketha EE · EE: Hanguranketha · EE Office

1Awarded 1Total
Hanguranketha 1 awarded of 1 Open filtered view
Category Total Awarded Pending Awarded % Estimate LKR Mn Contract LKR Mn Planned Exp Mn Actual Exp ex-VAT Planned % Actual %
Emergency 1 1 0 100% 44.7 47.8 23.6 — 72.8% 10.0%
DC 0 0 0 0% 0.0 0.0 — — — —
DC - Slope 0 0 0 0% 0.0 0.0 — — — —
PD(CP) 0 0 0 0% 0.0 0.0 — — — —
Hanguranketha 1 1 0 100% 44.7 47.8 23.6 0.0 0% of contract 72.8% 10.0%

Project-wise Progress · Hanguranketha EE · EE: Hanguranketha (1 projects in one graph)

Physical Actual vs Planned per project • Click bar to open project

Clear

Project-wise Physical Progress: Actual vs Planned (%) · Hanguranketha EE · EE: Hanguranketha

Average Physical Progress by EE Division · Hanguranketha EE · EE: Hanguranketha

Average District-wise Physical Progress (Nuwara Eliya District)

Nuwara Eliya district baseline — all categories · EE: Hanguranketha (consultant filter excluded for comparison)

At-Risk Projects · Hanguranketha EE · EE: Hanguranketha

0

No at-risk projects

No open high/critical issues or overdue projects in this view

Portfolio Timeline · 1 scheduled projects · Hanguranketha EE · EE: Hanguranketha Toggle
2026-07-30 today 2026-10-28
Portfolio · Awarded Works

Awarded Projects

1 projects

1/1
Contract No. Contract Name Progress Amount Status
RDA/DRP/CEN/NUE/HAN/57
Rehabilitation / Improvement of Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )
10%
47,755,538.96 Awarded
Showing 1–1 of 1