Project Monitoring Dashboard
Comprehensive overview of 0 infrastructure projects
under the Disaster Rehabilitation Programme.
Portfolio at a Glance
0 awarded works · Nuwara Eliya · EE: Nuwara Eliya
0
Awarded
9 total projects in portfolio
0.0 Mn
Contract Value
0
works in progress
0 completed
Avg Progress
0.0 Mn
Total Expenditure (excl. VAT)
0
Kick Off Pending
0 / 0 awarded
0
Mobilization Pending
0 / 0 awarded
0
Works Not Started
0 / 0 awarded
0
Completed
0 / 0 awarded
Portfolio Breakdown · Nuwara Eliya · EE: Nuwara Eliya · EE Office
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| DC | 9 | 0 | 9 | 0% | 6,206.9 | 0.0 | — | — | — | — |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| All Districts | 9 | 0 | 9 | 0% | 6,206.9 | 0.0 | 0.0 | 0.0 — | — | — |
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| DC | 9 | 0 | 9 | 0% | 6,206.9 | 0.0 | — | — | — | — |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| Nuwara Eliya | 9 | 0 | 9 | 0% | 6,206.9 | 0.0 | 0.0 | 0.0 — | — | — |
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 8 | 8 | 0 | 100% | 1,024.9 | 1,162.8 | 585.9 | 96.1 8% of contract | 74.4% | 22.6% |
| DC | 19 | 3 | 16 | 16% | 9,852.6 | 1,026.9 | 24.4 | — | 4.9% | 2.0% |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| PD(CP) | 2 | 0 | 2 | 0% | 62.4 | 0.0 | — | — | — | — |
| All EE Offices | 29 | 11 | 18 | 38% | 10,939.9 | 2,189.7 | 610.3 | 96.1 4% of contract | 55.4% | 17.0% |
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 3 | 3 | 0 | 100% | 435.8 | 369.1 | 210.9 | 14.1 4% of contract | 78.7% | 24.3% |
| DC | 6 | 2 | 4 | 33% | 2,767.1 | 979.2 | 24.4 | — | 7.4% | 3.0% |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| PD(CP) | 2 | 0 | 2 | 0% | 62.4 | 0.0 | — | — | — | — |
| Norwood | 11 | 5 | 6 | 45% | 3,265.3 | 1,348.3 | 235.3 | 14.1 1% of contract | 50.2% | 15.8% |
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| DC | 9 | 0 | 9 | 0% | 6,206.9 | 0.0 | — | — | — | — |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| Nuwara Eliya | 9 | 0 | 9 | 0% | 6,206.9 | 0.0 | 0.0 | 0.0 — | — | — |
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 4 | 4 | 0 | 100% | 544.4 | 745.9 | 351.4 | 82.0 11% of contract | 71.6% | 24.5% |
| DC | 1 | 1 | 0 | 100% | 0.0 | 47.7 | — | — | 0.0% | 0.0% |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| NuwaraEliya | 5 | 5 | 0 | 100% | 544.4 | 793.6 | 351.4 | 82.0 10% of contract | 57.3% | 19.6% |
| Category | Total | Awarded | Pending | Awarded % | Estimate LKR Mn | Contract LKR Mn | Planned Exp Mn | Actual Exp ex-VAT | Planned % | Actual % |
|---|---|---|---|---|---|---|---|---|---|---|
| Emergency | 1 | 1 | 0 | 100% | 44.7 | 47.8 | 23.6 | — | 72.8% | 10.0% |
| DC | 3 | 0 | 3 | 0% | 878.6 | 0.0 | — | — | — | — |
| DC - Slope | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| PD(CP) | 0 | 0 | 0 | 0% | 0.0 | 0.0 | — | — | — | — |
| Hanguranketha | 4 | 1 | 3 | 25% | 923.3 | 47.8 | 23.6 | 0.0 0% of contract | 72.8% | 10.0% |
Avg Physical Progress per EE Division · Nuwara Eliya · EE: Nuwara Eliya
No data available
Awarded projects will appear here
Financial Progress per EE Division (Mn) Excluding VAT · Nuwara Eliya · EE: Nuwara Eliya
No financial data available
Awarded projects will appear here
District-wise Physical Progress · Nuwara Eliya · EE: Nuwara Eliya
No district data available
Awarded projects will appear here
District-wise Financial Progress (Mn) · Nuwara Eliya · EE: Nuwara Eliya
No financial data available
Awarded projects will appear here
Consultant-wise Physical Progress · Nuwara Eliya · EE: Nuwara Eliya
No consultant data available
Awarded projects will appear here
Consultant-wise Financial Progress (Mn) · Nuwara Eliya · EE: Nuwara Eliya
No financial data available
Awarded projects will appear here
Project-wise Physical Progress: Actual vs Planned (%) · Nuwara Eliya · EE: Nuwara Eliya (0)
No data available
Awarded projects will appear here
Project-wise Financial Progress: Actual vs Planned (Mn) · Nuwara Eliya · EE: Nuwara Eliya (0)
No financial data available
Awarded projects will appear here
At-Risk Projects · Nuwara Eliya · EE: Nuwara Eliya
No at-risk projects
No open high/critical issues or overdue projects in this view
Awarded Projects
0 projects
| Contract No. | Contract Name | District | EE Division | Contractor | Consultant | Progress | Amount | Status | Mobilized | Kick Off | Active | Commenced | Scheduled End | Category |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|