DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 18 awarded projects

2026-11-05
00:40:25Live2026-11-05
0 / 18Advance Pendingpending advance projects / total projects
0 / 18IPC Pendingpending IPC projects / total projects
0 / 18Advance Paidadvance paid projects / total projects
0 / 18IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Badulla · District

579Projects23,829.3Contract Mn
Badulla 18 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn138.524.163% of contract14.4——————0.0%0.0%
Tender Below 50Mn11176.2125.671% of contract50.7——————27.3%0.0%
DL Stage 014139.7102.874% of contract36.8——————100.0%0.0%
DL Stage 02226.329.3111% of contract-3.0——————0.0%0.0%
DL Stage 0300.0——————————
DL Stage 0400.0——————————
PIU00.0——————————
Badulla18380.7281.874% of contract98.9000.0000.038.9%0.0%
Tender Above 50Mn1 project38.5Mn
63% paid24.1 Mn
Pending14.4Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn11 projects176.2Mn
71% paid125.6 Mn
Pending50.7Mn
Planned Fin27.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 014 projects139.7Mn
74% paid102.8 Mn
Pending36.8Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 022 projects26.3Mn
111% paid29.3 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Badulla18 projects380.7Mn
74% paid281.8 Mn
Pending98.9Mn
Planned Fin38.9%
Actual Fin0.0%

Avg Physical Progress per Province · Badulla

Graphs reflect current view:18 awarded · Badulla
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 218 projects (filtered from 579)

141–150/218 (filtered from 579)
ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
141RR/RDA/13/25/03/NP/MUL
Navatkadu Road
TMC Constructions
50,363,687.00————————————
142RR/RDA/13/25/06/NP/MUL
Pandaravanniyan Silaiyadi Road
Sun Constructions (Pvt) Ltd.
83,700,000.00————————————
143RR/RDA/13/25/07/NP/MUL
Kanagarayankulam District Boundary Road (Old Kandy road)
Sun Constructions (Pvt) Ltd.
159,972,500.00————————————
144RR/RDA/13/25/08/NP/MUL
Kumulamunai Akkarayan road
Nimna Holdings (Pvt) Ltd
148,861,042.00————————————
145RR/RDA/13/25/10/NP/MUL
Pandiyankulam Neddankandal Road
Nimna Holdings (Pvt) Ltd
144,696,282.50————————————
146RR/RDA/13/25/11/NP/MUL
Ethawetuvuwewa to Sampathnuwara
Nimna Holdings (Pvt) Ltd
110,422,944.50————————————
147RR/RDA/11/25/01/NP/MNR
Mahilankulam Pallamadhu road
George Steuart Engineering (Pvt)Ltd
189,602,588.30————————————
148RR/RDA/11/25/02/NP/MNR
Piramanayankulam Parappukadanthan road
George Steuart Engineering (Pvt)Ltd
169,538,631.82————————————
149RR/RDA/11/25/04/NP/MNR
Tharavankottai to Keeri Main Road
VN Construction JV
146,489,579.50————————————
150RR/RDA/11/25/07/NP/MNR
Avithappar Panimayam Internal Road with Culvert - Pesalai
VN Construction JV
—————————————
Total8,978,398,226.97——————————
—Mn
0%
—Mn
0%
Showing 141–150 of 218 projects · page 15/22