DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 15 awarded projects

2026-11-04
23:35:40Live2026-11-04
0 / 15Advance Pendingpending advance projects / total projects
0 / 15IPC Pendingpending IPC projects / total projects
0 / 15Advance Paidadvance paid projects / total projects
0 / 15IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Hambantota · District

579Projects23,829.3Contract Mn
Hambantota 15 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn00.0——————————
Tender Below 50Mn5153.627.418% of contract126.2——————89.0%0.0%
DL Stage 013153.2102.767% of contract50.5——————66.7%0.0%
DL Stage 02137.729.779% of contract8.0——————100.0%0.0%
DL Stage 031127.689.070% of contract38.6——————100.0%0.0%
DL Stage 045325.0184.957% of contract140.1——————20.0%0.0%
PIU00.0——————————
Hambantota15797.0433.754% of contract363.4000.0000.063.0%0.0%
Tender Above 50Mn0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn5 projects153.6Mn
18% paid27.4 Mn
Pending126.2Mn
Planned Fin89.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 013 projects153.2Mn
67% paid102.7 Mn
Pending50.5Mn
Planned Fin66.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project37.7Mn
79% paid29.7 Mn
Pending8.0Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 project127.6Mn
70% paid89.0 Mn
Pending38.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 045 projects325.0Mn
57% paid184.9 Mn
Pending140.1Mn
Planned Fin20.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Hambantota15 projects797.0Mn
54% paid433.7 Mn
Pending363.4Mn
Planned Fin63.0%
Actual Fin0.0%

Avg Physical Progress per Province · Hambantota

Graphs reflect current view:15 awarded · Hambantota
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 291 projects (filtered from 579)

31–40/291 (filtered from 579)
ActiveProgress 100–100%
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
31RR/RDA/STA II/16/25/04/AKK/A…
Lahugala Hulannuge Roundabout road
Zaka Engineering Consultancy
26,597,958.20————————————
32RR/RDA/16/25/10KM/06/AKK/AKK
Hulannuge School Road
Gama Construction & Consultant pvt Ltd
11,406,166.73————————————
33RR/RDA/16/25/10KM/09/AKK/AKK
Road behind Necode Institute (Navatkadu Akkarapattu)
SMA Careem Engineering Consultancy Servi…
15,228,903.25————————————
34RR/RDA/15/25/01/EP/BTC
Concreting to Vipulananthar road
SSK Construction
29,074,090.89————————————
35RR/RDA/15/25/07/EP/BTC
Concreting to Thakwa masjith Cross Road
Nazeeha Hardware and Construction
22,206,567.30————————————
36RR/RDA/17/25/01/EP/TRN
Pillayar Road Renovation
Rina Construction
23,425,921.56————————————
37RR/RDA/17/25/02/EP/TRN
Kathirkamathambi Road
Fareed
28,809,738.00————————————
38RR/RDA/17/25/03/EP/TRN
Hospital Road
Pragash Construction
18,557,253.77————————————
39RR/RDA/17/25/07/EP/TRN
Kanthamalawa Main Road
SSK Construction
9,161,570.00————————————
40RR/RDA/17/25/10/EP/TRN
From Medagama temple to Peramaduwa
Soyuru Sampath Construction & Suppliers
24,197,635.00————————————
Total8,230,991,569.86——————————
—Mn
0%
—Mn
0%
Showing 31–40 of 291 projects · page 4/30