Financial Dashboard

Monitor financial performance across 5 awarded projects

2026-11-05
04:23:35Live2026-11-05
0 / 5Advance Pendingpending advance projects / total projects
0 / 5IPC Pendingpending IPC projects / total projects
0 / 5Advance Paidadvance paid projects / total projects
0 / 5IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Uva Province · Monaragala · District

579Projects23,829.3Contract Mn
Monaragala 5 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn134.134.2100% of contract-0.1——————0.0%0.0%
Tender Below 50Mn00.0——————————
DL Stage 012138.7124.089% of contract14.7——————100.0%0.0%
DL Stage 02273.069.896% of contract3.1——————0.0%0.0%
DL Stage 0300.0——————————
DL Stage 0400.0——————————
PIU00.0——————————
Monaragala5245.8228.093% of contract17.7000.0000.040.0%0.0%
Tender Above 50Mn1 project34.1Mn
100% paid34.2 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 012 projects138.7Mn
89% paid124.0 Mn
Pending14.7Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 022 projects73.0Mn
96% paid69.8 Mn
Pending3.1Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Monaragala5 projects245.8Mn
93% paid228.0 Mn
Pending17.7Mn
Planned Fin40.0%
Actual Fin0.0%

Avg Physical Progress per Province · Uva Province · Monaragala

Graphs reflect current view:5 awarded · Uva Province · Monaragala
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

451–460/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
451RR/RDA/20/25/21
Pawithrapura Road
—
32,078,244.10————————————
452RR/RDA/20/25/08
Jaya mawatha sita Kaththaragama pansala dakwa margaya
—
15,557,589.26————————————
453RR/RDA/20/25/09
Padavi para Rambukepuwewa mansandiye sita Elapath wewa margaya dakwa margaya
—
36,917,003.94————————————
454RR/RDA/21/25/01
Ganangolla pradhana para sihala moola asala sita sirisena mahathage niwasa dakwa…
—
34,916,075.79————————————
455RR/GA/21/25/CC/13
Sathutugama Nidahas mawatha sanwardhanaya kireema
—
53,733,874.70————————————
456RR/RDA/20/25/17
Galwaduwawa Junction to Yaya 02 road of Thambuththegama Eppawala Road
—
64,398,698.77————————————
457RR/RDA/20/25/24
Konketiyawa School to Mayilankulama Vilage road
—
35,296,893.96————————————
458RR/RDA/21/25/AC/15
Aralaganwila Allewewa road Balance Section
—
51,779,609.70————————————
459RR/GA/21/25/CC/12
Girithale janapadaya pasal mawatha carpet kara ithiri kotasa wana D.G. Jayasiri …
—
42,689,736.99————————————
460RR/RDA/21/25/16
Diyabeduma to Jamburewela Road
—
122,382,954.72————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 451–460 of 579 projects · page 46/58