DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 10 awarded projects

2026-11-05
08:57:33Live2026-11-05
0 / 10Advance Pendingpending advance projects / total projects
0 / 10IPC Pendingpending IPC projects / total projects
0 / 10Advance Paidadvance paid projects / total projects
0 / 10IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · EE: Colombo · EE Office

567Projects20,718.2Contract Mn
Colombo 10 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn133.67.723% of contract25.9——————0.0%0.0%
Tender Below 50Mn353.118.234% of contract34.9——————0.0%0.0%
DL Stage 01117.510.962% of contract6.6——————100.0%0.0%
DL Stage 0213.6—3.6——————100.0%0.0%
DL Stage 0300.0——————————
DL Stage 04432.1—32.1——————0.0%0.0%
Colombo10139.936.826% of contract103.2000.0000.020.0%0.0%
Tender Above 50Mn1 project33.6Mn
23% paid7.7 Mn
Pending25.9Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn3 projects53.1Mn
34% paid18.2 Mn
Pending34.9Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project17.5Mn
62% paid10.9 Mn
Pending6.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project3.6Mn
0% paid0.0 Mn
Pending3.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 044 projects32.1Mn
0% paid0.0 Mn
Pending32.1Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Colombo10 projects139.9Mn
26% paid36.8 Mn
Pending103.2Mn
Planned Fin20.0%
Actual Fin0.0%

Avg Physical Progress per Province · EE: Colombo

Project-wise Financials · EE: Colombo (579 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Colombo (Mn · incl. VAT)

Scroll horizontally — 579 projects

Colombo Division · EE: Colombo (Mn · incl. VAT)

Colombo District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:10 awarded · EE: Colombo
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

221–230/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
221RR/RDA/12/25/18/NP/VVN
Nedunkerny North sandankulam Road
Yaso Engineering
32,829,160.10————————————
222RR/RDA/12/25/19/NP/VVN
Senaipilavu Road
Yaso Engineering
32,576,225.00————————————
223RR/RDA/12/25/20/NP/VVN
Puthiyakudiyiruppu parasankulam road
Bapithan Construction
23,259,239.30————————————
224RR/RDA/12/25/21/NP/VVN
Bagaswewa 01st 22nd lane
Bapithan Construction
22,749,983.30————————————
225RR/RDA/12/25/24/NP/VVN
Kanagarayankulam puthuvilankulam road (NVVNE073)
Bapithan Construction
31,165,786.30————————————
226RR/RDA/12/25/25/NP/VVN
2nd cross Lane Ginigathhena
Nimna Holdings (Pvt) Ltd
27,770,291.00————————————
227RR/RDA/12/25/26/NP/VVN
Cemetery Road
Ranasinghe Construction
17,011,533.00————————————
228RR/RDA/12/25/27/NP/VVN
From Acre 400 7th Lane to cross end of the 2nd internal road close to Andarawewa
Ranasinghe Construction
46,360,659.24————————————
229RR/RDA/12/25/28/NP/VVN
From Janaudanagama 2nd internal road to end of the free school
North Construction (Pvt) Ltd
26,569,012.25————————————
230RR/RDA/12/25/29/NP/VVN
Kalasiyambalawa Road
North Construction (Pvt) Ltd
13,504,281.45————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 221–230 of 579 projects · page 23/58