DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 9 awarded projects

2026-11-04
16:34:22Live2026-11-04
0 / 9Advance Pendingpending advance projects / total projects
0 / 9IPC Pendingpending IPC projects / total projects
0 / 9Advance Paidadvance paid projects / total projects
0 / 9IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · EE: Habarana · EE Office

567Projects20,718.2Contract Mn
Habarana 9 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn2103.322.922% of contract80.4——————50.0%0.0%
Tender Below 50Mn00.0——————————
DL Stage 01162.654.086% of contract8.6——————100.0%0.0%
DL Stage 02153.759.4111% of contract-5.7——————0.0%0.0%
DL Stage 033194.9159.882% of contract35.1——————0.0%0.0%
DL Stage 042197.1159.681% of contract37.5——————0.0%0.0%
Habarana9611.6455.775% of contract155.9000.0000.022.2%0.0%
Tender Above 50Mn2 projects103.3Mn
22% paid22.9 Mn
Pending80.4Mn
Planned Fin50.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project62.6Mn
86% paid54.0 Mn
Pending8.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project53.7Mn
111% paid59.4 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 033 projects194.9Mn
82% paid159.8 Mn
Pending35.1Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 042 projects197.1Mn
81% paid159.6 Mn
Pending37.5Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Habarana9 projects611.6Mn
75% paid455.7 Mn
Pending155.9Mn
Planned Fin22.2%
Actual Fin0.0%

Avg Physical Progress per Province · EE: Habarana

Project-wise Financials · EE: Habarana (218 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Habarana (Mn · incl. VAT)

Scroll horizontally — 218 projects

Habarana Division · EE: Habarana (Mn · incl. VAT)

Polonnaruwa District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:9 awarded · EE: Habarana
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 218 projects (filtered from 579)

11–20/218 (filtered from 579)
ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
11—
Development of the Dolapihilla road from Navinnapitiya via Deldeniya
Ajith Construction
65,808,186.50————————————
12—
Development of entrance roads, pedestrian rest areas and parking areas of the Sr…
Southern Group Civil Construction (Pvt) …
83,080,000.00————————————
13RR/RDA/05/25/09/CP/MTL
Ilukkumbura Samurdhi karyalaya asala Patti ela pilama dakwa
Pragathi Civil Contractor
38,748,820.00————————————
14RR/RDA/05/25/10/CP/MTL
Sonuththa pradana margaye Shailatharamaya idiriye sita 80 yaya dakwa
NAGMA ENGINEERING (PVT) LTD
56,167,707.75————————————
15RR/RDA/05/25/11/CP/MTL
Hunukete sita Elagala dakwa Pradana Margaya
Senerath Engineering (pvt) Ltd
82,470,143.89————————————
16RR/RDA/05/25/26/CP/MTL
Pallepola saukya karyalaye sita ekamuthugama dakwa margaya
Jayaru Engineering (Pvt) Ltd
18,760,083.54————————————
17RR/RDA/05/25/30/CP/MTL
Ganadewi pilimaya asala Kulathunga mahathage welanda sala dakwa
Lahiru Construction & Consultants (PVT) …
59,540,000.00————————————
18RR/RDA/06/25/32/CP/NE
Nanuoya Glaso pahala kotasa Margaya
wiscon (pvt) ltd
38,841,280.50————————————
19RR/RDA/06/25/34/CP/NE
Udupussellawa margaye Amasta handiye sita Ambagasdowa dakwa Margaya
NAGMA ENGINEERING (PVT) LTD
54,639,783.83————————————
20RR/RDA/06/25/38/CP/NE
Ketahira Gallella margya palama haraha Udagama dakwa Margaya
NAGMA ENGINEERING (PVT) LTD
38,465,634.79————————————
Total8,978,398,226.97——————————
—Mn
0%
—Mn
0%
Showing 11–20 of 218 projects · page 2/22