DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 6 awarded projects

2026-11-05
10:48:42Live2026-11-05
0 / 6Advance Pendingpending advance projects / total projects
0 / 6IPC Pendingpending IPC projects / total projects
0 / 6Advance Paidadvance paid projects / total projects
0 / 6IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · EE: Nuwara Eliya · EE Office

567Projects20,718.2Contract Mn
Nuwara Eliya 6 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn151.83.26% of contract48.5——————100.0%0.0%
Tender Below 50Mn138.84.512% of contract34.3——————100.0%0.0%
DL Stage 01165.376.6117% of contract-11.3——————100.0%0.0%
DL Stage 02140.745.3111% of contract-4.6——————100.0%0.0%
DL Stage 03218.914.476% of contract4.4——————100.0%0.0%
DL Stage 0400.0——————————
Nuwara Eliya6215.5144.167% of contract71.4000.0000.0100.0%0.0%
Tender Above 50Mn1 project51.8Mn
6% paid3.2 Mn
Pending48.5Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn1 project38.8Mn
12% paid4.5 Mn
Pending34.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project65.3Mn
117% paid76.6 Mn
Pending—
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project40.7Mn
111% paid45.3 Mn
Pending—
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 032 projects18.9Mn
76% paid14.4 Mn
Pending4.4Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Nuwara Eliya6 projects215.5Mn
67% paid144.1 Mn
Pending71.4Mn
Planned Fin100.0%
Actual Fin0.0%

Avg Physical Progress per Province · EE: Nuwara Eliya

Project-wise Financials · EE: Nuwara Eliya (291 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Nuwara Eliya (Mn · incl. VAT)

Scroll horizontally — 291 projects

Nuwara Eliya Division · EE: Nuwara Eliya (Mn · incl. VAT)

Nuwara Eliya District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:6 awarded · EE: Nuwara Eliya
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 291 projects (filtered from 579)

111–120/291 (filtered from 579)
ActiveProgress 100–100%
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
111RR/RDA/25/25/33/SBP/KGL
Rehabilitation of Kahatapanawa Kajugahamula road
Jayabima Engineering
12,423,785.00————————————
112RR/RDA/07/25/06/SP/GAL
Mulana Nagenahira ha Panwila Grama Niladari Wasam Sambandha wana athuru Margaya
Star Light Construction
13,805,759.00————————————
113RR/RDA/07/25/08/SP/GAL
Mahajana Mawatha Magurukaduwa Margaya Elpitiya Pitigala Pradhana Margaye sita Ma…
EHL Constructions
27,637,049.00————————————
114RR/RDA/07/25/11/SP/GAL
Elathota Pituwara Margaya Depasa Kanu ha Pathi Bami Yoda Carpet Kirima
Jayathissa Construction
20,801,618.20————————————
115RR/RDA/07/25/12/SP/GAL
Galandeniya Margaya
Star Light Construction
26,433,958.63————————————
116RR/RDA/07/25/15/SP/GAL
Dikhena Margaya
Thilak Kumara Builders
34,817,376.22————————————
117RR/RDA/07/25/20/SP/GAL
Road from Kammale Kadaya Junction to Udumalagala Juunction
Kumarage Enterprises(Pvt)Ltd
25,272,045.84————————————
118RR/RDA/25/08/03/SP/MTR
Wattakgoda Ayurvedha Rohala Margaya Sanwardanay kirima
Visula Construction
33,591,312.70————————————
119RR/RDA/25/08/08/SP/MTR
Asmagoda Galabadahena Margaya Sanwardanaya Palamu Adiyara
Induwara Construction
11,168,036.00————————————
120RR/RDA/25/08/10/SP/MTR
Arapotha Belideniya Margaya Carpet athura Sanwardanaya Kirima
Rathna Construction
22,859,983.85————————————
Total8,230,991,569.86——————————
—Mn
0%
—Mn
0%
Showing 111–120 of 291 projects · page 12/30