DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 80 awarded projects

2026-11-04
13:26:51Live2026-11-04
0 / 80Advance Pendingpending advance projects / total projects
0 / 80IPC Pendingpending IPC projects / total projects
0 / 80Advance Paidadvance paid projects / total projects
0 / 80IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Central Province · Province

579Projects23,829.3Contract Mn
Central Province 80 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn191,398.4290.621% of contract1,107.8——————73.5%0.0%
Tender Below 50Mn37912.8506.555% of contract406.4——————78.4%0.0%
PIU00.0——————————
Tender Total562,311.3797.134% of contract1,514.2000.0000.076.7%0.0%
Direct LabourDL Stage 019359.8323.890% of contract36.0——————100.0%0.0%
DL Stage 026212.7158.675% of contract54.1——————100.0%0.0%
DL Stage 038179.478.144% of contract101.3——————100.0%0.0%
DL Stage 04156.218.834% of contract37.3——————100.0%0.0%
Direct Labour Total24808.1579.372% of contract228.7000.0000.0100.0%0.0%
—Central Province803,119.31,376.444% of contract1,742.9000.0000.083.7%0.0%
Tender Above 50Mn19 projectsTender1,398.4Mn
21% paid290.6 Mn
Pending1,107.8Mn
Planned Fin73.5%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn37 projectsTender912.8Mn
55% paid506.5 Mn
Pending406.4Mn
Planned Fin78.4%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projectsTender0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 019 projectsDirect Labour359.8Mn
90% paid323.8 Mn
Pending36.0Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 026 projectsDirect Labour212.7Mn
75% paid158.6 Mn
Pending54.1Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 038 projectsDirect Labour179.4Mn
44% paid78.1 Mn
Pending101.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 041 projectDirect Labour56.2Mn
34% paid18.8 Mn
Pending37.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Central Province80 projects3,119.3Mn
44% paid1,376.4 Mn
Pending1,742.9Mn
Planned Fin83.7%
Actual Fin0.0%

Avg Physical Progress per Province · Central Province

Graphs reflect current view:80 awarded · Central Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 291 projects (filtered from 579)

21–30/291 (filtered from 579)
ActiveProgress 100–100%
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
21RR/RDA/05/25/19/CP/MTL
Katudeniya bahukarya godanagilla asala Hettiyawatta dakwa margaya
Ajith Construction
13,129,506.50————————————
22RR/RDA/05/25/20/CP/MTL
Harispattuwa margaya arambaka mansandiye sita Thusitha maranadara godanagilla da…
Ajith Construction
15,584,937.50————————————
23RR/RDA/05/25/22/CP/MTL
Sigirimulla sita Mailetthewa Aluthyaya dakwa margaya
Asiri Contractor and Designers
33,057,264.90————————————
24RR/RDA/05/25/24/CP/MTL
Pahala Hombawa palama dakwa Daduwagolla kanaththa langa sita
Ajith Construction
35,817,952.50————————————
25RR/RDA/05/25/27/CP/MTL
Welemulla sita Kandewaththa
Ajith Construction
23,207,525.00————————————
26RR/RDA/05/25/29/CP/MTL
Pitawala handiye sita pitawala desata
Lahiru Construction & Consultants (PVT) …
37,136,372.90————————————
27RR/RDA/06/25/37/CP/NE
Gewal wissa handiye sita Bogalkanda dakwa Margaye asiru sthan
Ajith Construction
28,282,100.00————————————
28RR/RDA/16/25/04/AKK/AMP
Pokunugama near Mr. Dinesh Tharaga House to Road (From Pokunugama Pre School to …
Harischandra Idikirim
6,435,000.00————————————
29RR/RDA/16/25/01/AKK/AMP
Samanalathenna- Road from House No.63 To the Monastery Muwagammana -From First L…
Vithu Construction
21,336,681.87————————————
30RR/RDA/STA II/16/25/02/AKK/A…
Concreting entrance road with culvert at Dehiaththakandiya Kelegama
Vithu Construction
30,737,790.60————————————
Total8,230,991,569.86——————————
—Mn
0%
—Mn
0%
Showing 21–30 of 291 projects · page 3/30