DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 80 awarded projects

2026-11-04
19:20:30Live2026-11-04
0 / 80Advance Pendingpending advance projects / total projects
0 / 80IPC Pendingpending IPC projects / total projects
0 / 80Advance Paidadvance paid projects / total projects
0 / 80IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Central Province · Province

579Projects23,829.3Contract Mn
Central Province 80 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn191,398.4290.621% of contract1,107.8——————73.5%0.0%
Tender Below 50Mn37912.8506.555% of contract406.4——————78.4%0.0%
PIU00.0——————————
Tender Total562,311.3797.134% of contract1,514.2000.0000.076.7%0.0%
Direct LabourDL Stage 019359.8323.890% of contract36.0——————100.0%0.0%
DL Stage 026212.7158.675% of contract54.1——————100.0%0.0%
DL Stage 038179.478.144% of contract101.3——————100.0%0.0%
DL Stage 04156.218.834% of contract37.3——————100.0%0.0%
Direct Labour Total24808.1579.372% of contract228.7000.0000.0100.0%0.0%
—Central Province803,119.31,376.444% of contract1,742.9000.0000.083.7%0.0%
Tender Above 50Mn19 projectsTender1,398.4Mn
21% paid290.6 Mn
Pending1,107.8Mn
Planned Fin73.5%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn37 projectsTender912.8Mn
55% paid506.5 Mn
Pending406.4Mn
Planned Fin78.4%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projectsTender0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 019 projectsDirect Labour359.8Mn
90% paid323.8 Mn
Pending36.0Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 026 projectsDirect Labour212.7Mn
75% paid158.6 Mn
Pending54.1Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 038 projectsDirect Labour179.4Mn
44% paid78.1 Mn
Pending101.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 041 projectDirect Labour56.2Mn
34% paid18.8 Mn
Pending37.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Central Province80 projects3,119.3Mn
44% paid1,376.4 Mn
Pending1,742.9Mn
Planned Fin83.7%
Actual Fin0.0%

Avg Physical Progress per Province · Central Province

Graphs reflect current view:80 awarded · Central Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 218 projects (filtered from 579)

181–190/218 (filtered from 579)
ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
181RR/RDA/08/25/18/SP/MTR
Dekatukella Margaya Pethibemma sahithawa Sanwardanaya kirima
Dashodhaya (Pvt)Ltd
4,080,866.90————————————
182RR/RDA/09/25/08/SP/HMB
Carpeting Pissubedda Medagamgoda road
Samarasinghe Construction(Pvt)Ltd
28,923,336.75————————————
183RR/RDA/09/25/09/SP/HMB
Development of the road in front of Godawela School to Ambussa Wela
A.T.L. Construction
34,500,631.00————————————
184RR/RDA/09/25/11/SP/HMB
Development of Walasmulla Daluwakgoda School Road
Samarasinghe Construction(Pvt)Ltd
34,814,777.80————————————
185RR/RDA/09/25/13/SP/HMB
Development of the road from Puak Dandawa near Aligerappa house through Weerasij…
A.T.L. Construction
23,847,807.50————————————
186RR/RDA/22/25/07/UP/BDL
Tharuna Govipola Margaye ithiri Kotasa Sanwardanaya Kirieema
Samadhi Construction
13,290,035.01————————————
187RR/RDA/22/25/22/UP/BDL
Achchupatti Margaya
Priyankara Industries and Contractors
25,269,262.70————————————
188RR/RDA/01/25/14/WP/COL
Development of the section from Arangala Bridge to Mihindu Mawatha in Malabe Wes…
W.A. Perera & Company (Pvt) Ltd.
33,591,596.50————————————
189RR/RDA/01/25/19WP/COL
Puwakpitiya Dharmalapala Mawatha Main Road Development of the road from High Lev…
Asela Construction
9,189,060.00————————————
190RR/RDA/01/25/26/WP/COL
Boraluwathenna Pahala Uda Road
Next Engineering Services (PVT) LTD
21,870,721.40————————————
Total8,978,398,226.97——————————
—Mn
0%
—Mn
0%
Showing 181–190 of 218 projects · page 19/22