DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 80 awarded projects

2026-11-05
00:40:55Live2026-11-05
0 / 80Advance Pendingpending advance projects / total projects
0 / 80IPC Pendingpending IPC projects / total projects
0 / 80Advance Paidadvance paid projects / total projects
0 / 80IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Central Province · Province

579Projects23,829.3Contract Mn
Central Province 80 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn191,398.4290.621% of contract1,107.8——————73.5%0.0%
Tender Below 50Mn37912.8506.555% of contract406.4——————78.4%0.0%
PIU00.0——————————
Tender Total562,311.3797.134% of contract1,514.2000.0000.076.7%0.0%
Direct LabourDL Stage 019359.8323.890% of contract36.0——————100.0%0.0%
DL Stage 026212.7158.675% of contract54.1——————100.0%0.0%
DL Stage 038179.478.144% of contract101.3——————100.0%0.0%
DL Stage 04156.218.834% of contract37.3——————100.0%0.0%
Direct Labour Total24808.1579.372% of contract228.7000.0000.0100.0%0.0%
—Central Province803,119.31,376.444% of contract1,742.9000.0000.083.7%0.0%
Tender Above 50Mn19 projectsTender1,398.4Mn
21% paid290.6 Mn
Pending1,107.8Mn
Planned Fin73.5%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn37 projectsTender912.8Mn
55% paid506.5 Mn
Pending406.4Mn
Planned Fin78.4%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projectsTender0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 019 projectsDirect Labour359.8Mn
90% paid323.8 Mn
Pending36.0Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 026 projectsDirect Labour212.7Mn
75% paid158.6 Mn
Pending54.1Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 038 projectsDirect Labour179.4Mn
44% paid78.1 Mn
Pending101.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 041 projectDirect Labour56.2Mn
34% paid18.8 Mn
Pending37.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Central Province80 projects3,119.3Mn
44% paid1,376.4 Mn
Pending1,742.9Mn
Planned Fin83.7%
Actual Fin0.0%

Avg Physical Progress per Province · Central Province

Graphs reflect current view:80 awarded · Central Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

481–490/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
481RR/RDA/19/25/25
Development of Mada Koswadiya Bogaha Road
—
25,235,881.81————————————
482RR/RDA/18/25/314
Road from Nugawela Junction in Walagane to Maspotha Crematorium via Temple
—
41,562,875.57————————————
483RR/RDA/18/25/309
From near Kongaha in Waudagama on the Katupotha Waudagama Wanduressegama road ne…
—
45,888,080.58————————————
484RR/RDA/18/25/317
Lakee Land Road in Wilattawa Division
—
9,799,762.91————————————
485RR/RDA/18/25/319
Kabaledevgama 3rd Lane and 4 Lane in Kaballewa Division of Kaballewa Division
—
21,709,247.87————————————
486RR/RDA/18/25/311
Road from Kopihena Junction to Dangolla in Damunugala Division of Piduruwella Di…
—
55,494,114.67————————————
487RR/RDA/18/25/312
Junction in front of Narampola Thoraya Muslim College to Budanapartiya Road via …
—
43,368,925.99————————————
488RR/RDA/19/25/36
Renovation of Warusavithana Laboratory Road
—
19,592,732.06————————————
489RR/RDA/19/25/35
Carpeting & Development of Kolithatissa Mawatha
—
10,359,335.01————————————
490RR/RDA/10/25/21
3rd Cross Street
—
11,072,958.55————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 481–490 of 579 projects · page 49/58