DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 50 awarded projects

2026-11-04
17:33:01Live2026-11-04
0 / 50Advance Pendingpending advance projects / total projects
0 / 50IPC Pendingpending IPC projects / total projects
0 / 50Advance Paidadvance paid projects / total projects
0 / 50IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Sabaragamuwa Province · Province

579Projects23,829.3Contract Mn
Sabaragamuwa Province 50 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn6435.6154.235% of contract281.3——————66.7%0.0%
Tender Below 50Mn29634.2195.831% of contract438.4——————80.7%0.0%
PIU00.0——————————
Tender Total351,069.7350.033% of contract719.8000.0000.078.3%0.0%
Direct LabourDL Stage 015184.5141.877% of contract42.7——————100.0%0.0%
DL Stage 024119.8102.986% of contract16.9——————100.0%0.0%
DL Stage 03234.814.843% of contract20.0——————100.0%0.0%
DL Stage 044335.055.216% of contract279.9——————100.0%0.0%
Direct Labour Total15674.1314.747% of contract359.5000.0000.0100.0%0.0%
—Sabaragamuwa Province501,743.9664.638% of contract1,079.2000.0000.084.8%0.0%
Tender Above 50Mn6 projectsTender435.6Mn
35% paid154.2 Mn
Pending281.3Mn
Planned Fin66.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn29 projectsTender634.2Mn
31% paid195.8 Mn
Pending438.4Mn
Planned Fin80.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projectsTender0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 015 projectsDirect Labour184.5Mn
77% paid141.8 Mn
Pending42.7Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 024 projectsDirect Labour119.8Mn
86% paid102.9 Mn
Pending16.9Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 032 projectsDirect Labour34.8Mn
43% paid14.8 Mn
Pending20.0Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 044 projectsDirect Labour335.0Mn
16% paid55.2 Mn
Pending279.9Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Sabaragamuwa Province50 projects1,743.9Mn
38% paid664.6 Mn
Pending1,079.2Mn
Planned Fin84.8%
Actual Fin0.0%

Avg Physical Progress per Province · Sabaragamuwa Province

Graphs reflect current view:50 awarded · Sabaragamuwa Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

551–560/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
551RR/RDA/23/25/04
Walawegaga Asala (Nildiya Mankada) Sita Udawalawa Bant eka Dakwa
—
74,104,374.63————————————
552RR/RDA/22/25/13
Peessa Pradana Margaye Abalan wu Ellanda Marga Kotasa
—
13,192,586.35————————————
553RR/RDA/22/25/10
Kosgolla Edaru Ulpatha Margaya
—
13,085,885.70————————————
554RR/RDA/23/25/03
Liyangolla Lolla Margaya
—
38,879,897.00————————————
555RR/RDA/23/25/02
Uduwara wewa Handiya sita Athula Margaya
—
34,079,767.34————————————
556RR/RDA/01/25/11
Vijitha Salawa asala sita Kothalawala Vidyalaya Asalin Gothami Viharaya dakva Ma…
—
17,512,654.33————————————
557RR/RDA/01/25/07
428/B Ihala Kosgama Grama Niladhari Wasame Praja Shalawa Pahala Margaya
—
51,557,606.95————————————
558RR/RDA/02/25/02
Development from the road in front of Kanti Teacher's house onwards to Vivekaram…
—
10,523,274.77————————————
559RR/RDA/02/25/01
Heendeniya Dumriya Sthanaya Dakwa Margaya
—
13,144,147.11————————————
560RR/RDA/02/25/04
Delpe Kadawara sita Nelumwaththa margaya arambaye sita Dewadasa mahathage niwasa…
—
26,006,255.54————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 551–560 of 579 projects · page 56/58