DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 19 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:19 awarded · Western Province · Colombo
70.4% awarded

0

Awarded

27 total projects 27 roads in portfolio

849.3M

849.3 Mn

Contract Value

Spent 12.1% Remaining 87.9%
Avg
71.3%

7

works in progress

11 completed

Avg Progress

103.0M

103.0 Mn

Total Expenditure (incl. VAT)

12.1% of contract incl. VAT
94.7%

0

On Progress

18 / 19 awarded

0%

0

Delay

0 / 19 awarded

0%

0

Critical Delay

0 / 19 awarded

Portfolio Breakdown · Western Province · Colombo · District

55Awarded71Total
Colombo 19 awarded of 27 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn21150%113.933.6—7.723% of contract0.0%68.0%
Tender Below 50Mn116555%173.686.6—18.221% of contract0.0%79.0%
DL Stage 01220100%69.169.169.162.691% of contract100.0%100.0%
DL Stage 02220100%20.020.020.08.241% of contract100.0%100.0%
DL Stage 03110100%8.08.08.06.379% of contract100.0%100.0%
DL Stage 04770100%52.7632.2——0.0%45.7%
PIU0000%0.00.0————
Not Specified2020%0.00.0————
Colombo2719870%437.3849.397.0103.012% of contract26.3%71.7%

Avg Physical Progress per EE Division · Western Province · Colombo

Portfolio Timeline· 15 scheduled projects · Western Province · Colombo Toggle
Portfolio · Awarded Works

Awarded Projects

11 projects

11/11 (filtered)

Filter awarded works

11 matching projects1 active

ActiveProgress 100–100%
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/01/25/03/WP/COLRR/RDA/01/25/03
Appropriate development of road from Maligagodella lake crossing near Isuri Motors to junction with Chandrika Kumaratunga Mawatha
100%
23,009,836.0531,303,935.95Awarded
2RR/RDA/01/25/09/WP/COLRR/RDA/01/25/09
Kottawa Malabe Road Sirimalwatta 1 Main road carpeted and developed
100%
2,424,881.232,804,484.03Awarded
3RR/RDA/01/25/12/WP/COLRR/RDA/01/25/12
550 A Lakshapathi North Sri Lanka Army Electrical and Mechanical Engineering Base Workshop (Katupedda) to be carpeted and developed from Galle Road.
100%
8,465,142.7311,014,256.76Awarded
4RR/RDA/01/25/11—
Vijitha Salawa asala sita Kothalawala Vidyalaya Asalin Gothami Viharaya dakva Margaya
100%
17,512,654.3317,512,654.33Awarded
5RR/RDA/01/25/07—
428/B Ihala Kosgama Grama Niladhari Wasame Praja Shalawa Pahala Margaya
100%
51,557,606.9551,557,606.95Awarded
6RR/RDA/01/25/02—
Paving and developing the road from North Borella Ganga Lower Vivekaramaya Temple to Siwali Lane No. 241/35D.
100%
3,636,186.593,636,186.59Awarded
7RR/RDA/01/25/06—
Development of Rambutan gahamula Suramya Mawatha using carpet in Magammana East Grama Niladhari Domain
100%
16,341,118.2716,341,118.27Awarded
8RR/RDA/01/25/17—
Access road to Polgasowita Dikhena Aranya
100%
7,965,231.107,965,231.10Awarded
9RR/RDA/01/25/16—
Bangalawa Road from 01st Gate to 04th Gate
100%
18,170,451.8218,170,451.82Awarded
10RR/RDA/01/25/24—
Development of the road from the beginning of the Horahena road from Wanaguru Mawatha in the Hokandara East Division to the Hokandara Pasmanhandiya with a carpet
100%
3,140,831.063,140,831.06Awarded
11RR/RDA/01/26/10KM/04—
Carpeting and development of Vijithapura Liyanage Mawatha and 3rd Lane
100%
1,560,361.911,560,361.91Awarded
Showing 1–11 of 11
Per page:
Source: DRRRP • 27 projects • Data updated 2026-11-02 10:30 • 19:02:57