DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 5 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:5 awarded · Hambantota · EE: Hambantota

Portfolio Breakdown · Hambantota · EE: Hambantota · EE Office

15Awarded15Total
Hambantota 5 awarded of 5 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Below 50Mn0000%0.00.0————
DL Stage 01220100%78.478.474.460.377% of contract50.0%100.0%
DL Stage 02110100%37.737.737.729.779% of contract100.0%100.0%
DL Stage 030000%0.00.0————
DL Stage 04220100%121.3121.354.8119.899% of contract50.0%95.0%
Hambantota550100%237.4237.4166.9209.888% of contract60.0%98.0%

Avg Physical Progress per EE Division · Hambantota · EE: Hambantota

Portfolio Timeline· 3 scheduled projects · Hambantota · EE: Hambantota Toggle
2025-06-21 today2026-11-04
Portfolio · Awarded Works

Awarded Projects

4 projects

4/4 (filtered)

Filter awarded works

4 matching projects1 active

ActiveOn Progress
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/08/25/Si—
Sithulpauwa Rajamaha Viharaye Katharagama Para
100%
3,969,390.343,969,390.34Awarded
2RR/RDA/09/25/01—
Karametiya Road
100%
74,446,690.1274,446,690.12Awarded
3RR/RDA/09/25/02—
Wam Iwura Janawasa Margaya
100%
37,666,563.4937,666,563.49Awarded
4RR/RDA/09/25/12—
Development of the road from Lunugamwehera Jadura Lake to Udaeva
92%
66,506,406.5766,506,406.57Awarded
Showing 1–4 of 4
Per page:
Source: DRRRP • 5 projects • Data updated 2026-11-02 10:30 • 10:41:02