Portfolio Breakdown · Hambantota · EE: Tangalle · EE Office

15Awarded15Total
Tangalle 10 awarded of 10 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Below 50Mn550100%204.8153.6136.327.418% of contract89.0%59.5%
DL Stage 01110100%74.874.874.842.457% of contract100.0%100.0%
DL Stage 020000%0.00.0————
DL Stage 03110100%127.6127.6127.689.070% of contract100.0%95.0%
DL Stage 04330100%203.7203.7—65.132% of contract0.0%85.0%
Tangalle10100100%610.9559.7338.7223.940% of contract64.5%74.8%

Avg Physical Progress per EE Division · Hambantota · EE: Tangalle

Portfolio Timeline· 10 scheduled projects · Hambantota · EE: Tangalle Toggle
Portfolio · Awarded Works

Awarded Projects

4 projects

4/4 (filtered)

Filter awarded works

4 matching projects1 active

ActiveOn Progress
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/08/25/04—
Vigamuwa Pattiyapola Road from Vigamuwa School
100%
74,802,039.6674,802,039.66Awarded
2RR/RDA/09/25/06—
Raluwa main road
70%
17,377,865.9917,377,865.99Awarded
3RR/RDA/09/25/14—
Development of road near Olu ara School
90%
101,801,692.33101,801,692.33Awarded
4RR/RDA/09/25/10—
Development of Valasmulla Pallekanda road from 3 km post to 5 km post
95%
84,525,263.2384,525,263.23Awarded