DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 15 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-02 10:30Live
Graphs reflect current view:15 awarded · Jaffna · EE: Jaffna
88.2% awarded
0
Awarded
17 total projects 17 roads in portfolio
Awarded projects15
RR/RDA/10/25/01/NP/JFNMaveli Periyathurai Road. 3.6509RR/RDA/10/25/03/NP/JFNNavalar RoadRR/RDA/10/25/04/NP/JFNAluminium Factory RoadRR/RDA/10/25/05/NP/JFNRenovation of Kokkuruniya VeethyRR/RDA/10/25/06/NP/JFNRenovation of West beach RoadRR/RDA/10/25/08/NP/JFNRenovation of Ilanthaikulam RoadRR/RDA/10/25/10/NP/JFNNayanmar RoadRR/RDA/10/25/11/NP/JFNAmman RoadRR/RDA/10/25/13/NP/JFNlnbacholai Road (Iththiyadi Muthali Kovilady - Inbacholai Road)RR/RDA/10/25/14/NP/JFNPankuru VeethyRR/RDA/10/25/15/NP/JFNKadavaippulam RoadRR/RDA/10/25/16/NP/JFNKalai Makal RoadRR/RDA/10/25/18/NP/JFNAtchuvely Industrial RoadRR/RDA/10/25/17College RoadRR/RDA/10/25/12Anaikoddai - Kakaithivu Road
Click to filter the awarded table
554.1M
554.1 Mn
Contract Value
Awarded projects15
RR/RDA/10/25/01/NP/JFNMaveli Periyathurai Road. 3.6509RR/RDA/10/25/03/NP/JFNNavalar RoadRR/RDA/10/25/04/NP/JFNAluminium Factory RoadRR/RDA/10/25/05/NP/JFNRenovation of Kokkuruniya VeethyRR/RDA/10/25/06/NP/JFNRenovation of West beach RoadRR/RDA/10/25/08/NP/JFNRenovation of Ilanthaikulam RoadRR/RDA/10/25/10/NP/JFNNayanmar RoadRR/RDA/10/25/11/NP/JFNAmman RoadRR/RDA/10/25/13/NP/JFNlnbacholai Road (Iththiyadi Muthali Kovilady - Inbacholai Road)RR/RDA/10/25/14/NP/JFNPankuru VeethyRR/RDA/10/25/15/NP/JFNKadavaippulam RoadRR/RDA/10/25/16/NP/JFNKalai Makal RoadRR/RDA/10/25/18/NP/JFNAtchuvely Industrial RoadRR/RDA/10/25/17College RoadRR/RDA/10/25/12Anaikoddai - Kakaithivu Road
Click to filter the awarded table
Avg
84%
4
works in progress
11 completed
Avg Progress
Awarded projects15
RR/RDA/10/25/01/NP/JFNMaveli Periyathurai Road. 3.6509RR/RDA/10/25/03/NP/JFNNavalar RoadRR/RDA/10/25/04/NP/JFNAluminium Factory RoadRR/RDA/10/25/05/NP/JFNRenovation of Kokkuruniya VeethyRR/RDA/10/25/06/NP/JFNRenovation of West beach RoadRR/RDA/10/25/08/NP/JFNRenovation of Ilanthaikulam RoadRR/RDA/10/25/10/NP/JFNNayanmar RoadRR/RDA/10/25/11/NP/JFNAmman RoadRR/RDA/10/25/13/NP/JFNlnbacholai Road (Iththiyadi Muthali Kovilady - Inbacholai Road)RR/RDA/10/25/14/NP/JFNPankuru VeethyRR/RDA/10/25/15/NP/JFNKadavaippulam RoadRR/RDA/10/25/16/NP/JFNKalai Makal RoadRR/RDA/10/25/18/NP/JFNAtchuvely Industrial RoadRR/RDA/10/25/17College RoadRR/RDA/10/25/12Anaikoddai - Kakaithivu Road
Click to filter the awarded table
201.4M
201.4 Mn
Total Expenditure (incl. VAT)
Awarded projects15
RR/RDA/10/25/01/NP/JFNMaveli Periyathurai Road. 3.6509RR/RDA/10/25/03/NP/JFNNavalar RoadRR/RDA/10/25/04/NP/JFNAluminium Factory RoadRR/RDA/10/25/05/NP/JFNRenovation of Kokkuruniya VeethyRR/RDA/10/25/06/NP/JFNRenovation of West beach RoadRR/RDA/10/25/08/NP/JFNRenovation of Ilanthaikulam RoadRR/RDA/10/25/10/NP/JFNNayanmar RoadRR/RDA/10/25/11/NP/JFNAmman RoadRR/RDA/10/25/13/NP/JFNlnbacholai Road (Iththiyadi Muthali Kovilady - Inbacholai Road)RR/RDA/10/25/14/NP/JFNPankuru VeethyRR/RDA/10/25/15/NP/JFNKadavaippulam RoadRR/RDA/10/25/16/NP/JFNKalai Makal RoadRR/RDA/10/25/18/NP/JFNAtchuvely Industrial RoadRR/RDA/10/25/17College RoadRR/RDA/10/25/12Anaikoddai - Kakaithivu Road
Click to filter the awarded table
80%
0
On Progress
12 / 15 awarded
On Progress (incl. completed)12
RR/RDA/10/25/01/NP/JFNMaveli Periyathurai Road. 3.6509RR/RDA/10/25/03/NP/JFNNavalar RoadRR/RDA/10/25/04/NP/JFNAluminium Factory RoadRR/RDA/10/25/05/NP/JFNRenovation of Kokkuruniya VeethyRR/RDA/10/25/08/NP/JFNRenovation of Ilanthaikulam RoadRR/RDA/10/25/10/NP/JFNNayanmar RoadRR/RDA/10/25/11/NP/JFNAmman RoadRR/RDA/10/25/13/NP/JFNlnbacholai Road (Iththiyadi Muthali Kovilady - Inbacholai Road)RR/RDA/10/25/15/NP/JFNKadavaippulam RoadRR/RDA/10/25/16/NP/JFNKalai Makal RoadRR/RDA/10/25/17College RoadRR/RDA/10/25/12Anaikoddai - Kakaithivu Road
Click to filter the awarded table
0%
0
Delay
0 / 15 awarded
Delay0
No projects
Click to filter the awarded table
20%
0
Critical Delay
3 / 15 awarded
Critical Delay3
RR/RDA/10/25/06/NP/JFNRenovation of West beach RoadRR/RDA/10/25/14/NP/JFNPankuru VeethyRR/RDA/10/25/18/NP/JFNAtchuvely Industrial Road
Click to filter the awarded table
73.3%
0
Completed
11 / 15 awarded
Completed11
RR/RDA/10/25/03/NP/JFNNavalar RoadRR/RDA/10/25/04/NP/JFNAluminium Factory RoadRR/RDA/10/25/05/NP/JFNRenovation of Kokkuruniya VeethyRR/RDA/10/25/08/NP/JFNRenovation of Ilanthaikulam RoadRR/RDA/10/25/10/NP/JFNNayanmar RoadRR/RDA/10/25/11/NP/JFNAmman RoadRR/RDA/10/25/13/NP/JFNlnbacholai Road (Iththiyadi Muthali Kovilady - Inbacholai Road)RR/RDA/10/25/15/NP/JFNKadavaippulam RoadRR/RDA/10/25/16/NP/JFNKalai Makal RoadRR/RDA/10/25/17College RoadRR/RDA/10/25/12Anaikoddai - Kakaithivu Road
Click to filter the awarded table
Portfolio Breakdown · Jaffna · EE: Jaffna · EE Office
Avg Physical Progress per EE Division · Jaffna · EE: Jaffna
Portfolio Timeline· 14 scheduled projects · Jaffna · EE: Jaffna Toggle
2025-06-21 today2026-11-04
Portfolio · Awarded Works
Awarded Projects
11 projects
Filter awarded works
11 matching projects1 active
| # | Contract No. | Package No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|---|---|
| 1 | RR/RDA/10/25/03/NP/JFN | RR/RDA/10/25/03 | Navalar Road | 100% | 7,919,722.64 | 16,240,094.76 | Awarded |
| 2 | RR/RDA/10/25/04/NP/JFN | RR/RDA/10/25/04 | Aluminium Factory Road | 100% | 36,973,948.00 | 56,580,112.16 | Awarded |
| 3 | RR/RDA/10/25/05/NP/JFN | RR/RDA/10/25/05 | Renovation of Kokkuruniya Veethy | 100% | 22,247,557.75 | 34,746,312.40 | Awarded |
| 4 | RR/RDA/10/25/08/NP/JFN | RR/RDA/10/25/08 | Renovation of Ilanthaikulam Road | 100% | 12,089,810.15 | 17,821,627.52 | Awarded |
| 5 | RR/RDA/10/25/10/NP/JFN | RR/RDA/10/25/10 | Nayanmar Road | 100% | 17,917,437.01 | 27,107,876.22 | Awarded |
| 6 | RR/RDA/10/25/11/NP/JFN | RR/RDA/10/25/11 | Amman Road | 100% | 14,588,981.00 | 19,749,993.06 | Awarded |
| 7 | RR/RDA/10/25/13/NP/JFN | RR/RDA/10/25/13 | lnbacholai Road (Iththiyadi Muthali Kovilady - Inbacholai Road) | 100% | 22,527,821.25 | 33,467,961.12 | Awarded |
| 8 | RR/RDA/10/25/15/NP/JFN | RR/RDA/10/25/15 | Kadavaippulam Road | 100% | 7,712,452.00 | 12,352,166.19 | Awarded |
| 9 | RR/RDA/10/25/16/NP/JFN | RR/RDA/10/25/16 | Kalai Makal Road | 100% | 17,670,712.18 | 25,146,295.80 | Awarded |
| 10 | RR/RDA/10/25/17 | — | College Road | 100% | 35,288,918.91 | 35,288,918.91 | Awarded |
| 11 | RR/RDA/10/25/12 | — | Anaikoddai - Kakaithivu Road | 100% | 34,361,480.40 | 34,361,480.40 | Awarded |
Showing 1–11 of 11
Source: DRRRP • 17 projects • Data updated 2026-11-02 10:30 • 10:38:04 System live • Sri Lanka • 1 districts