DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 11 awarded projects

2026-11-04
18:41:52Live2026-11-04
0 / 11Advance Pendingpending advance projects / total projects
0 / 11IPC Pendingpending IPC projects / total projects
6 / 11Advance Paidadvance paid projects / total projects
4 / 11IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

158.2 Mn

158.20 Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Emergency · North Central Province · Province

144Projects24,785.9Contract Mn
Reset
North Central Province 11 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency11846.2158.219% of contract—66101.24432.898.2%15.8%
DC - Roads00.0——————————
DC - Slope00.0——————————
PD(CP) - Slope00.0——————————
North Central Province11846.2158.219% of contract0.066101.24432.898.2%15.8%
Emergency11 projects846.2Mn
19% paid158.2 Mn
Pending—
Planned Fin98.2%
Actual Fin15.8%
Advance & IPC
Advance paid6 proj · 101.2 Mn
IPC paid4 proj · 32.8 Mn
Open filtered view
DC - Roads0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
North Central Province11 projects846.2Mn
19% paid158.2 Mn
Pending0.0Mn
Planned Fin98.2%
Actual Fin15.8%

Avg Physical Progress per Province · Emergency · North Central Province

Graphs reflect current view:11 awarded · Emergency · North Central Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 171 projects

21–30/171

Filter financial register

171 matching projects

S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
21RDA/DRP/CEN/MTL/NAL/51
Rehabilitation /Improvement of Retaining wall , drains and shoulder construction…
Platinum Holdings Lanka (Private) Limite…
17,458,592.782,700,844.133,186,956.07——2,081,765.362,456,483.122,488,679.182,936,641.434,782,609.492,488,679.18
5.64Mn
32.3%
Watch
8.58Mn
49.1%
22RDA/DRP/CEN/NUE/HAN/57
Rehabilitation / Improvement of Keerthibandarapura Naranthalawa Road ( B -511…
Samindra Construction
47,755,538.967,835,575.379,245,978.94——————7,835,575.37—
9.25Mn
19.4%
Behind
9.25Mn
19.4%
23RDA/DRP/CEN/NUE/NUE/60R
Rehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (A005) (40+75…
KSJ Construction (Pvt) Ltd
336,313,078.73————————————
24RDA/DRP/CEN/NUE/NUE/66
Rehabilitation / Improvement of Nuwara Eliya Town Road (0+000 - 1+695 ) (0+000…
KSJ Construction (Pvt) Ltd
161,841,095.7028,951,653.7634,162,951.44——14,629,744.0917,263,098.028,358,462.699,862,985.9843,581,397.858,358,462.69
51.43Mn
31.8%
Watch
61.29Mn
37.9%
25RDA/DRP/CEN/NUE/NUE/67
Rehabilitation / Improvement of Harangala - Kalapitiya - Kumbaloluwa Road (10+4…
KSJ Construction (Pvt) Ltd
239,417,811.3443,196,511.1850,971,883.16——43,235,770.8951,018,210.14——86,432,282.07—
101.99Mn
42.6%
On Track
101.99Mn
42.6%
26RDA/DRP/CEN/NUE/NUE/68
Rehabilitation / Improvement of Thawalanthenna Thalawakelle Road (0+000 - 8+000…
Green Scene Construction (Pvt) Ltd
213,999,600.0138,371,088.0245,277,883.86——6,376,287.747,524,019.188,205,562.669,682,563.9444,747,375.768,205,562.66
52.80Mn
24.7%
Watch
62.48Mn
29.2%
27RDA/DRP/CEN/NUE/NUE/69
Rehabilitation / Improvement of Ulapane Pussallawa Road (6+440 - 15+950)
Southern Group Civil Construction (Pvt) …
266,045,892.1947,095,300.0055,572,454.00——36,285,409.1342,816,782.78——83,380,709.13—
98.39Mn
37%
Watch
98.39Mn
37%
28RDA/DRP/CEN/NUE/NUE/86
Rehabilitation / Improvement of Approch road to R'way station (Watagoda/ Thalawa…
Pragathi Civil Construction
33,765,626.86————————————
29RDA/DRP/CEN/NUE/NUR/97
Rehabilitation/Improvement of Nawalapitiya Ginigathena Road (B-319)(7+200-12+200…
Jayawansa Construction (Pvt) Ltd
93,758,217.7614,149,694.3416,696,639.33——————14,149,694.34—
16.70Mn
17.8%
Behind
16.70Mn
17.8%
30RDA/DRP/CEN/NUE/NUR/98
Rehabilitation/Improvement Harangala Kalapitiya Road (B-148) (0+000-10+700), App…
Pragathi Civil Construction
188,617,394.68————————————
Total34,005,299,486.172,787,819,645.293,289,427,166.63113,218,826.01133,598,214.691,049,943,508.601,238,847,524.5163,842,351.1873,647,937.023,837,763,153.89177,061,177.19
4,528.27Mn
13.3%
4,735.52Mn
13.9%
Showing 21–30 of 171 projects · page 3/18