DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 3 awarded projects

2026-11-04
19:02:06Live2026-11-04
0 / 3Advance Pendingpending advance projects / total projects
1 / 3IPC Pendingpending IPC projects / total projects
2 / 3Advance Paidadvance paid projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

2.9 Mn

2.94 Mn

IPCs Pend (incl. VAT)

23.1 Mn

23.13 Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Nalanda EE · Consultant

44Projects11,748.0Contract Mn
Reset
Nalanda EE 3 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency3112.620.218% of contract2.92210.0327.169.5%15.2%
DC - Roads00.0——————————
DC - Slope00.0——————————
PD(CP) - Slope00.0——————————
Nalanda EE3112.620.218% of contract2.92210.0327.169.5%15.2%
Emergency3 projects112.6Mn
18% paid20.2 Mn
Pending2.9Mn
Planned Fin69.5%
Actual Fin15.2%
Advance & IPC
Advance paid2 proj · 10.0 Mn
IPC paid2 proj · 7.1 Mn
Open filtered view
DC - Roads0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Nalanda EE3 projects112.6Mn
18% paid20.2 Mn
Pending2.9Mn
Planned Fin69.5%
Actual Fin15.2%

Avg Physical Progress per Province · Nalanda EE

Project-wise Financials · Nalanda EE (136 Projects)

Clear

Project-wise Contract Value vs. Expenditure and Pending Payments · Nalanda EE (Mn · incl. VAT)

Scroll horizontally — 136 projects

Nalanda EE Division · Nalanda EE (Mn · incl. VAT)

Matale District Summary (Mn · incl. VAT)

District baseline — overall all categories (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:3 awarded · Nalanda EE
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 136 projects (filtered from 171)

1–10/136 (filtered from 171)

Filter financial register

136 matching projects1 active

ActiveIn progress
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
1RDA/DRP/CEN/KDY/KAD/11
Rehabilitation / Improvement of Nawalapitiya - Dolosbage Road ( B -318) ( 10+50…
Tiasa Construction (Pvt) Ltd
193,404,194.9633,346,525.5439,348,900.14——15,954,390.2918,826,180.55——49,300,915.83—
58.18Mn
30.1%
Watch
58.18Mn
30.1%
2RDA/DRP/CEN/KDY/KAN/14
Rehabilitation /Improvement of Katugasthota Medawala road ( B 0206)( 0 + 000 - …
Alucon Industries (Pvt) Ltd
74,836,014.77————————————
3RDA/DRP/CEN/KDY/KDY/15
Rehabilitation / Improvement of Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)
Jayawansa Construction (Pvt) Ltd
79,071,437.68————————————
4RDA/DRP/CEN/KDY/KDY/19
Rehabilitation / Improvement of Poojapitiya Alawathugoda road ( B 377) ( 0+000 -…
Jayawansa Construction (Pvt) Ltd
67,935,586.77————————————
5RDA/DRP/CEN/KDY/KUN/20
Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuw…
Samindra Construction
31,558,227.98————————————
6RDA/DRP/CEN/KDY/KUN/21
Improvement of Pitiyegedara-Waththegama-Iriyagasthenna Road (0+000-5+400)
Jayasinghe Construction (Pvt) Ltd
257,721,453.9646,231,491.4254,553,159.88————8,483,606.8010,010,656.0246,231,491.428,483,606.80
54.55Mn
21.2%
Watch
64.56Mn
25.1%
7RDA/DRP/CEN/KDY/KUN/22
Improvement to Damaged Road Section on Weeragantota - Randenigala Road. (From CH…
SD Civil Construction (Pvt) Ltd
224,968,435.7840,192,882.6347,427,601.50——34,738,972.1940,991,987.18——74,931,854.82—
88.42Mn
39.3%
Watch
88.42Mn
39.3%
8RDA/DRP/CEN/KDY/KUN/24R
Rehabilitation / Improvement of Flood damage on Katugastota - Madawala - Bambere…
Nimsara Construction & Engineering (Pvt)…
79,507,501.11————————————
9RDA/DRP/CEN/KDY/KUN/25
Construction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LH…
S N O Builders (Pvt) Ltd
157,909,825.0128,346,587.8033,448,973.60——25,922,264.5430,502,481.3810,705,591.4711,041,226.8354,268,852.3410,705,591.47
63.95Mn
40.5%
On Track
74.99Mn
47.5%
10RDA/DRP/CEN/KDY/KUN/27
Improvement to Structures on Kandy - Jaffna Road 6+500 - 9+910
Gihan Enterprise
113,434,139.4020,128,022.3723,751,066.40——2,934,355.863,462,539.91——23,062,378.23—
27.21Mn
24%
Watch
27.21Mn
24%
Total25,015,709,448.332,771,382,827.733,270,031,721.91113,218,826.01133,598,214.691,001,703,559.511,181,924,384.5863,842,351.1873,647,937.023,773,086,387.24177,061,177.19
4,451.96Mn
17.8%
4,659.20Mn
18.6%
Showing 1–10 of 136 projects · page 1/14