DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 10 awarded projects

2026-11-04
21:23:23Live2026-11-04
0 / 10Advance Pendingpending advance projects / total projects
1 / 10IPC Pendingpending IPC projects / total projects
1 / 10Advance Paidadvance paid projects / total projects
1 / 10IPCs PaidIPC paid projects / total projects
29.0 Mn

28.95 Mn

Advance Paid (excl. VAT)

14.6 Mn

14.63 Mn

IPCs Paid (excl. VAT)

43.6 Mn

43.58 Mn

Total Paid (excl. VAT)

51.4 Mn

51.43 Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

9.9 Mn

9.86 Mn

IPCs Pend (incl. VAT)

61.3 Mn

61.29 Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Team Leader · Nuwara Eliya · Consultant

20Projects7,381.9Contract Mn
Reset
Team Leader 10 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency2498.251.410% of contract9.91129.02114.652.8%8.7%
DC - Roads64,137.5————————0.0%0.0%
DC - Slope2597.0————————0.0%0.0%
PD(CP) - Slope00.0——————————
Team Leader105,232.651.41% of contract9.91129.02114.610.6%0.8%
Emergency2 projects498.2Mn
10% paid51.4 Mn
Pending9.9Mn
Planned Fin52.8%
Actual Fin8.7%
Advance & IPC
Advance paid1 proj · 29.0 Mn
IPC paid1 proj · 14.6 Mn
Open filtered view
DC - Roads6 projects4,137.5Mn
0% paid0.0 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope2 projects597.0Mn
0% paid0.0 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Team Leader10 projects5,232.6Mn
1% paid51.4 Mn
Pending9.9Mn
Planned Fin10.6%
Actual Fin0.8%

Avg Physical Progress per Province · Team Leader · Nuwara Eliya

Project-wise Financials · Team Leader · Nuwara Eliya (171 Projects)

Clear

Project-wise Contract Value vs. Expenditure and Pending Payments · Team Leader · Nuwara Eliya (Mn · incl. VAT)

Scroll horizontally — 171 projects

Team Leader · Team Leader · Nuwara Eliya (Mn · incl. VAT)

Nuwara Eliya District Summary (Mn · incl. VAT)

District baseline — overall all categories (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:10 awarded · Team Leader · Nuwara Eliya
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 171 projects

121–130/171

Filter financial register

171 matching projects

S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
121RDA/DRP/SAB/RAT/EMB/07
Rehabilitation / Improvement of Pelmadulla - Embilipitiya-Nonagama Road (37+000-…
Anura Construction
276,583,785.23————————————
122RDA/DRP/SAB/RAT/EMB/09
Rehabilitation / Improvement of Pelmadulla - Embilipitiya - Naonagama Road (47+1…
Anura Construction
269,913,795.48————————————
123RDA/DRP/SAB/RAT/EMB/11
Rehabilitation / Improvement of Weligepola-Hadagiriya - Kapugala (2+000-11+000)
D K S Construction
273,586,576.2249,239,013.9458,102,036.46——————49,239,013.94—
58.10Mn
21.2%
Watch
58.10Mn
21.2%
124RDA/DRP/WP/COL/COL/07
Rehabilitation / Improvement of Colombo Hanwella Road (0+370 - 20+400)
INK Engineering
146,665,907.47————5,477,974.446,464,009.84——5,477,974.44—
6.46Mn
4.4%
Behind
6.46Mn
4.4%
125RDA/DRP/EAS/TRI/TRI/03
Rehabilitation / Improvement of Town & Gravets Road (B140) (Fort Fredrick Road) …
Motec Engineering & Construction
37,828,051.78————15,201,592.3817,937,879.01——15,201,592.38—
17.94Mn
47.4%
On Track
17.94Mn
47.4%
126RDA/DRP/EAS/TRI/TRI/04
Rehabilitation / Improvement of Town & Gravets Road (B140) (Inner Harbour Road) …
Motec Engineering & Construction
40,407,339.17————————————
127RDA/DRP/NWP/KURU/MAHO/06R
Rehabilitation / Improvement of Kadigawa Bridge Approaches on Pahala Mawathagama…
RCDC Construction Company (Pvt) Ltd
75,025,358.95————————————
128RDA/DRP/NWP/CHI/CHI/08
Rehabilitation / Improvement of Baththuluoya - Udappuwa - Andimunai Road (B614) …
ST MARY Construction
83,944,711.21————15,224,674.7617,965,116.22——15,224,674.76—
17.97Mn
21.4%
Watch
17.97Mn
21.4%
129RDA/DPR/NCP/ANU/ANU/01
Rehabilitation / Improvement of Andarawewa - Balaluwewa Road (B501) (21+330 - 21…
Ranuja Construction
99,497,834.48————————————
130RDA/DRP/NCP/POL/HAB/04
Rehabilitation / Improvement of washed out section between 30/1 & 30/2 Bridges o…
Lahiru Construction and Consultants (Pvt…
49,203,550.22————————————
Total34,005,299,486.172,787,819,645.293,289,427,166.63113,218,826.01133,598,214.691,049,943,508.601,238,847,524.5163,842,351.1873,647,937.023,837,763,153.89177,061,177.19
4,528.27Mn
13.3%
4,735.52Mn
13.9%
Showing 121–130 of 171 projects · page 13/18