Pending—
Planned Fin100.0%
Actual Fin31.3%
Advance & IPC
Advance paid2 proj · 28.0 Mn
IPC paid2 proj · 22.1 Mn
Monitor financial performance across 2 awarded projects
160.34 Mn
Total Contract
28.05 Mn
Advance Paid (excl. VAT)
22.08 Mn
IPCs Paid (excl. VAT)
50.13 Mn
Total Paid (excl. VAT)
59.15 Mn
Total Paid (incl. VAT)
— Mn
Advance Pend (incl. VAT)
— Mn
IPCs Pend (incl. VAT)
59.15 Mn
Total (Paid+Pend) (incl. VAT)
Paid incl + Adv Pend incl + IPC Pend incl
31.3%
Financial Progress (excl. VAT)
Total (Paid+Pend) excl / Contract
100%
Planned Financial Progress
Planned share of contract value
Advance payments, IPCs & expenditure per awarded project · 92 projects (filtered from 171)
Filter financial register
92 matching projects1 active
| S/N | Contract No | Contract Name | Contractor | Contract (LKR) | Advance Paid (excl. VAT) | Advance Paid (incl. VAT) | Advance Pend (excl. VAT) | Advance Pend (incl. VAT) | IPCs Paid (excl. VAT) | IPCs Paid (incl. VAT) | IPCs Pend (excl. VAT) | IPCs Pend (incl. VAT) | Overall Expenditure (excl. VAT) | Pending Payments (excl. VAT) | Financial Progress | Financial Progress with Outstanding |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 51 | RDA/DRP/WP/GAM/NIT/22 | Rehabilitation / Improvement of Delgoda Dompe Giridara Road (Selected Sections … | Senarath Engineering (Pvt) Ltd | 264,745,054.48 | 47,651,364.45 | 56,228,610.05 | — | — | — | — | — | — | 47,651,364.45 | — | 56.23Mn Watch21.2% | 56.23Mn 21.2% |
| 52 | RDA/DRP/WP/GAM/NIT/23 | Rehabilitation / Improvement of Kalagedihena Veyangoda Road (0+000 -3+000), Pas… | Senarath Engineering (Pvt) Ltd | 258,218,314.97 | 45,755,884.54 | 53,991,943.76 | — | — | — | — | — | — | 45,755,884.54 | — | 53.99Mn Watch20.9% | 53.99Mn 20.9% |
| 53 | RDA/DRP/SAB/KEG/RUW/30 | Rehabilitation of Dehiovita - Daraniyagala - Nooriya Road (from 23+850 to 27+960… | Accon Engineering (Pvt) Ltd | 169,223,910.80 | 30,441,983.79 | 35,921,540.87 | — | — | 9,989,836.66 | 11,788,007.26 | — | — | 40,431,820.45 | — | 47.71Mn Watch28.2% | 47.71Mn 28.2% |
| 54 | RDA/DRP/SAB/KEG/RUW/31 | Rehabilitation of Kegalle - Bulathkohupitiya - Karawanella Road due to catastrop… | Tudawe Brothers (Pvt) Ltd | 269,890,586.86 | 48,845,015.80 | 57,637,118.64 | — | — | 8,891,636.65 | 10,492,131.25 | — | — | 57,736,652.45 | — | 68.13Mn Watch25.2% | 68.13Mn 25.2% |
| 55 | RDA/DRP/WP/COL/AVI/02 | Rehabilitation / Improvement of Damage Sections on Colombo - Hanwella Low Level … | Keangnam Engineering & Construction (Pvt… | 279,374,027.90 | — | — | — | — | 6,828,549.84 | 8,057,688.81 | — | — | 6,828,549.84 | — | 8.06Mn Behind2.9% | 8.06Mn 2.9% |
| 56 | RDA/DRP/WP/COL/AVI/03 | Rehabilitation / Improvement and Asphalt Overlaying on Colombo - Horana Road (B0… | Keangnam Engineering & Construction (Pvt… | 176,739,557.41 | 382,642.19 | 451,517.79 | — | — | 838,664.06 | 989,623.60 | — | — | 1,221,306.25 | — | 1.44Mn Behind0.8% | 1.44Mn 0.8% |
| 57 | RDA/DRP/WP/COL/AVI/04 | Rehabilitation / Improvement and Asphalt Overlaying on Mampe Kottawa Road (B267)… | Keangnam Engineering & Construction (Pvt… | 94,697,340.01 | 17,192,698.18 | 20,287,383.86 | — | — | 30,212,899.20 | 35,651,221.05 | — | — | 47,405,597.38 | — | 55.94Mn On Track59.1% | 55.94Mn 59.1% |
| 58 | RDA/DRP/WP/COL/AVI/05 | Rehabilitation / Improvement and Asphalt Overlaying on Panagoda Henpita Road (B3… | Keangnam Engineering & Construction (Pvt… | 225,228,168.18 | — | — | — | — | 1,635,814.91 | 1,930,261.59 | — | — | 1,635,814.91 | — | 1.93Mn Behind0.9% | 1.93Mn 0.9% |
| 59 | RDA/DRP/NWP/KURU/KURU/04 | Rehabilitation / Improvement of Muththettugala Hiripitiya Road (B300) (10+880 … | TMC Construction (Pvt) Ltd | 97,503,423.17 | 16,053,895.12 | 18,943,596.24 | — | — | 11,350,228.21 | 13,393,269.29 | — | — | 27,404,123.33 | — | 32.34Mn Watch33.2% | 32.34Mn 33.2% |
| 60 | RDA/DRP/NWP/KURU/MAHO/05 | Rehabilitation / Improvement of Galgamuwa - Nikawewa Road (B126) (6+000-20+000),… | St. Anthony's Construction | 151,515,024.36 | 27,548,186.25 | 32,506,859.78 | — | — | — | — | — | — | 27,548,186.25 | — | 32.51Mn Watch21.5% | 32.51Mn 21.5% |
| Total | 16,799,029,680.14 | 2,276,780,837.16 | 2,686,401,372.89 | — | — | 905,188,809.07 | 1,068,036,979.06 | 52,935,451.96 | 60,777,795.94 | 3,181,969,646.23 | 52,935,451.96 | 3,754.44Mn 22.3% | 3,815.22Mn 22.7% | |||