DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 7 awarded projects

2026-11-05
02:13:12Live2026-11-05
0 / 7Advance Pendingpending advance projects / total projects
0 / 7IPC Pendingpending IPC projects / total projects
3 / 7Advance Paidadvance paid projects / total projects
0 / 7IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

91.8 Mn

91.83 Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · EE: Norwood · EE Office

155Projects31,163.5Contract Mn
Reset
Norwood 7 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency3369.134.09% of contract—2228.9———96.2%7.8%
DC - Roads2979.257.86% of contract—1149.0———1.9%5.0%
DC - Slope2484.8————————0.0%0.0%
PD(CP) - Slope00.0——————————
Norwood71,833.091.85% of contract0.03377.8000.041.8%4.2%
Emergency3 projects369.1Mn
9% paid34.0 Mn
Pending—
Planned Fin96.2%
Actual Fin7.8%
Advance & IPC
Advance paid2 proj · 28.9 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Roads2 projects979.2Mn
6% paid57.8 Mn
Pending—
Planned Fin1.9%
Actual Fin5.0%
Advance & IPC
Advance paid1 proj · 49.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope2 projects484.8Mn
0% paid0.0 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Norwood7 projects1,833.0Mn
5% paid91.8 Mn
Pending0.0Mn
Planned Fin41.8%
Actual Fin4.2%

Avg Physical Progress per Province · EE: Norwood

Project-wise Financials · EE: Norwood (92 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Norwood (Mn · incl. VAT)

Scroll horizontally — 92 projects

Norwood Division · EE: Norwood (Mn · incl. VAT)

Nuwara Eliya District Summary (Mn · incl. VAT)

District baseline — overall all categories (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:7 awarded · EE: Norwood
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 92 projects (filtered from 171)

71–80/92 (filtered from 171)

Filter financial register

92 matching projects1 active

ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
71RDA/DRP/SAB/RAT/EMB/08
Rehabilitation / Improvement of Pelmadulla - Embilipitiya - Naonagama Road (AA01…
Anura Construction
259,436,963.3546,754,356.9855,170,141.24——————46,754,356.98—
55.17Mn
21.3%
Watch
55.17Mn
21.3%
72RDA/DRP/SAB/RAT/EMB/10
Rehabilitation / Improvement of Pelmadulla - Embilipitiya - Nonagama Road (AA018…
Kanwel Constructions & Civil Engineering…
260,776,583.4347,155,924.2655,643,990.62——11,394,017.6413,444,940.82——58,549,941.90—
69.09Mn
26.5%
Watch
69.09Mn
26.5%
73RDA/DRP/EAS/BAT/BAT/01
Rehabilitation / Improvement and Surfacing from 56+900 km to 58+300km and from 5…
S S K Construction
113,074,919.76————45,270,508.3753,419,199.87——45,270,508.37—
53.42Mn
47.2%
On Track
53.42Mn
47.2%
74RDA/DRP/SAB/RAT/EMB/05
Rehabilitation / Improvement of Pelmadulla-Embilipitiya-Nonagama Road (30+000-32…
Anura Construction
248,600,718.52————————————
75RDA/DRP/SAB/RAT/EMB/06
Rehabilitation / Improvement of Pelmadulla - Embilipitiya-Nonagama Road (33+500-…
Anura Construction
237,998,681.32————————————
76RDA/DRP/SAB/RAT/EMB/07
Rehabilitation / Improvement of Pelmadulla - Embilipitiya-Nonagama Road (37+000-…
Anura Construction
276,583,785.23————————————
77RDA/DRP/SAB/RAT/EMB/09
Rehabilitation / Improvement of Pelmadulla - Embilipitiya - Naonagama Road (47+1…
Anura Construction
269,913,795.48————————————
78RDA/DRP/SAB/RAT/EMB/11
Rehabilitation / Improvement of Weligepola-Hadagiriya - Kapugala (2+000-11+000)
D K S Construction
273,586,576.2249,239,013.9458,102,036.46——————49,239,013.94—
58.10Mn
21.2%
Watch
58.10Mn
21.2%
79RDA/DRP/WP/COL/COL/07
Rehabilitation / Improvement of Colombo Hanwella Road (0+370 - 20+400)
INK Engineering
146,665,907.47————5,477,974.446,464,009.84——5,477,974.44—
6.46Mn
4.4%
Behind
6.46Mn
4.4%
80RDA/DRP/EAS/TRI/TRI/04
Rehabilitation / Improvement of Town & Gravets Road (B140) (Inner Harbour Road) …
Motec Engineering & Construction
40,407,339.17————————————
Total16,799,029,680.142,276,780,837.162,686,401,372.89——905,188,809.071,068,036,979.0652,935,451.9660,777,795.943,181,969,646.2352,935,451.96
3,754.44Mn
22.3%
3,815.22Mn
22.7%
Showing 71–80 of 92 projects · page 8/10