DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 8 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 15:53Live
Graphs reflect current view:8 awarded · EE: Gampaha
0%

0

On Progress

0 / 8 awarded

0%

0

Delay

0 / 8 awarded

0%

0

Completed

0 / 8 awarded

Portfolio Breakdown · EE: Gampaha · EE Office

155Awarded237Total
Gampaha 8 awarded of 11 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Emergency118373%2,346.41,447.41,447.4253.117% of contract100.0%20.0%
DC - Roads0000%0.00.0————
DC - Slope0000%0.00.0————
PD(CP) - Slope0000%0.00.0————
Gampaha118373%2,346.41,447.41,447.4253.117% of contract100.0%20.0%

Avg Physical Progress per EE Division · EE: Gampaha

At-Risk Projects · EE: Gampaha

8
Portfolio Timeline· 8 scheduled projects · EE: Gampaha Toggle
Portfolio · Awarded Works

Awarded Projects

8 projects

8/8 (filtered)

Filter awarded works

8 matching projects1 active

ActiveIn progress
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/WP/GAM/NEG/19
Rehabilitation / Improvement of Negombo-Mirigama Road (5+000-6+000) and Negombo-Giriulla Road (29+000-34+000)
20%
206,184,462.57222,010,882.78Awarded
RDA/DRP/WP/GAM/NIT/21
Rehabilitation / Improvement of Hanwella Urapola Road (3+000 - 10+100), Structure Construction on Delgoda Dompe Giridara Road (0+000- 10+070) and Urapola Wathuragama Road (0+000- 7+080 ) and Drain Construction on Negombo-Mirigama road (21+000 - 30+580)
28%
221,768,903.84231,075,356.57Awarded
RDA/DRP/WP/GAM/GAM/10
Rehabilitation / Improvement of Old Minuwangoda Gampaha - Miriswatta Road (9+000 - 10+000) and Minuwangoda - Gampaha Road (0+000 - 5+300)
2%
92,177,672.52110,481,340.20Awarded
RDA/DRP/WP/GAM/GAM/12
Rehabilitation / Improvement of Acces Road to Peliyagoda interchange (0+000 - 2+100), Colombo - Kandy Road (6+500-19+000) and Kelaniya - Waragoda Road (0+000-3+220)
2%
151,956,608.92170,010,323.36Awarded
RDA/DRP/WP/GAM/NIT/20
Rehabilitation / Improvement of Bothale Mirigama Road (3+750-4+800), Warakapola Kandalama Road (7+000-8+000), (8+500-9+000) & (9+500-10+900), Negombo Mirigama Road and Construction of Gabion Wall on Colombo - Kandy Road at 54+950,Warakapola Kandalama Road at Culvert No. 10/4 LHS and Widening of Culvert Nos. 4/1 LHS 4/3 Bothsides and Reconstruction of Culvert No. 4/2 on Veyangoda Banduragoda Road
46%
217,881,464.96245,395,696.16Awarded
RDA/DRP/WP/GAM/NIT/22
Rehabilitation / Improvement of Delgoda Dompe Giridara Road (Selected Sections between 2+000-12+100)
1%
264,745,054.48294,920,837.23Awarded
RDA/DRP/WP/GAM/NIT/23
Rehabilitation / Improvement of Kalagedihena Veyangoda Road (0+000 -3+000), Pasyala Attanagalla Road (0+000 - 6+400) and Colombo - Kandy Road (38+620 -38+720)
1%
258,218,314.97305,207,472.65Awarded
RDA/DRP/WP/GAM/GAM/13
Rehabilitation / Improvement and Culvert Constructions on Aluthgama- Vigoda Road at 1+650, on Katunayake - Veyangoda Road at 15+940, on Minuwangoda - Miriswatta - Katana Road at 3+700, on Dunagaha- Nilpanagoda Road at 4+900, on Kadawatha - Mawaramandiya Road at 2+800 and on Makola - Udupila Road at 3+200
60%
34,489,854.8539,535,250.16Awarded
Showing 1–8 of 8
Per page:
Source: DRRRP • 11 projects • Data updated 2026-11-02 15:53 • 09:49:21