DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 3 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-02 15:53Live
Graphs reflect current view:3 awarded · EE: Hanguranketha
25% awarded
0
Awarded
12 total projects in portfolio
Awarded projects3
RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )RDA/DC/DRP/SLOPE/CP/NUE/HAN/PACKAGE 26ERDA/DC/DRP/SLOPE/CP/NUE/HAN/PACKAGE 26C
Click to filter the awarded table
560.1M
560.1 Mn
Contract Value
Awarded projects3
RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )RDA/DC/DRP/SLOPE/CP/NUE/HAN/PACKAGE 26ERDA/DC/DRP/SLOPE/CP/NUE/HAN/PACKAGE 26C
Click to filter the awarded table
Avg
30%
1
works in progress
0 completed
Avg Progress
Awarded projects3
RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )RDA/DC/DRP/SLOPE/CP/NUE/HAN/PACKAGE 26ERDA/DC/DRP/SLOPE/CP/NUE/HAN/PACKAGE 26C
Click to filter the awarded table
9.2M
9.2 Mn
Total Expenditure (incl. VAT)
Awarded projects3
RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )RDA/DC/DRP/SLOPE/CP/NUE/HAN/PACKAGE 26ERDA/DC/DRP/SLOPE/CP/NUE/HAN/PACKAGE 26C
Click to filter the awarded table
0%
0
On Progress
0 / 3 awarded
On Progress (incl. completed)0
No projects
Click to filter the awarded table
0%
0
Delay
0 / 3 awarded
Delay0
No projects
Click to filter the awarded table
33.3%
0
Critical Delay
1 / 3 awarded
Critical Delay1
Click to filter the awarded table
0%
0
Completed
0 / 3 awarded
Completed0
No projects
Click to filter the awarded table
Portfolio Breakdown · EE: Hanguranketha · EE Office
Avg Physical Progress per EE Division · EE: Hanguranketha
At-Risk Projects · EE: Hanguranketha
Portfolio Timeline· 1 scheduled projects · EE: Hanguranketha Toggle
2026-07-30 today2026-11-04
Portfolio · Awarded Works
Awarded Projects
3 projects
Filter awarded works
3 matching projects
| Contract No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|
| RDA/DRP/CEN/NUE/HAN/57 | Rehabilitation / Improvement of Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 ) | 30% | 47,755,538.96 | 44,694,533.62 | Awarded |
| RDA/DC/DRP/SLOPE/CP/NUE/HAN/PACKAGE 26E | REHABILITATION OF SELECTED ROAD SECTIONS ON THENNEKUMBURA RIKILLAGASKADA RAGALA ROAD (B413) (50+100-70+950 ) AND SLOPE FAILURES DUE TO "DITWAH" CYCLONE-PACKAGE 26E | 0% | 332,123,863.50 | 322,400,000.00 | Awarded |
| RDA/DC/DRP/SLOPE/CP/NUE/HAN/PACKAGE 26C | MITIGATION FOR FAILURE LOCATIONS ALONG THENNEKUMBURA RIKILLAGASKADA RAGALA ROAD (B413) (48/11 - 48/12) & (67/10 - 67 km) DUE TO "DITWAH" CYCLONE-PACKAGE 26C | 0% | 180,175,018.14 | 159,300,000.00 | Awarded |
Showing 1–3 of 3
Source: DRRRP • 12 projects • Data updated 2026-11-02 15:53 • 08:57:42 System live • Sri Lanka • 1 districts