DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 24 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 15:53Live
Graphs reflect current view:24 awarded · Nuwara Eliya

Portfolio Breakdown · Nuwara Eliya · District

171Awarded266Total
Nuwara Eliya 24 awarded of 56 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp ex-VATPlanned %Actual %
Emergency10100100%2,032.01,668.31,329.5294.818% of contract89.4%44.0%
DC - Roads1981142%11,271.25,116.614.4—0.5%5.8%
DC - Slope2361726%8,208.01,731.6——0.0%0.0%
PD(CP) - Slope4040%102.30.0————
Nuwara Eliya56243243%21,613.58,516.51,344.0294.83% of contract37.4%20.3%

Avg Physical Progress per EE Division · Nuwara Eliya

Portfolio Timeline· 13 scheduled projects · Nuwara Eliya Toggle
Portfolio · Awarded Works

Awarded Projects

4 projects

4/4 (filtered)

Filter awarded works

4 matching projects1 active

ActiveOn Progress
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/CEN/NUE/NUE/60R
Rehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (A005) (40+750 - 42+850)
10%
336,313,078.73338,287,510.33Awarded
RDA/DC/DRP/CP/NE/NRW/02
REHABILITATION/ IMPROVEMENT OF APPROCH ROAD TO LAXAPANA POWER HOUSE ROAD CH 6+100 - 12+000
9%
374,859,845.10348,620,000.00Awarded
RDA/DC/DRP/CP/NE/NE/04
REHABILITAION/ IMPROVEMENTS OF LADY MACALUMS DRIVE ROAD (2+850 - 5+600KM)
1%
636,338,397.00560,630,000.00Awarded
RDA/DC/DRP/CP/NE/NRW/03
REHABILITATION/ IMPROVEMENT TO ROZELLA RAILWAY STATION ROAD (0+000 - 3+300) KM AND WATAWALA RAILWAY STATION ROAD (0+000 - 1+850) KM
19%
604,298,969.28509,310,000.00Awarded