Dashboard Physical Progress

Physical Progress

1

Awarded Projects

1 / 1

In Progress

22.0%

Avg Progress

0

Overdue

Awarded Projects Summary

1 projects

XLSX Clear Showing 1 of 1
Contract No. Contractor Commencement Date Completion Date Overall Progress Action
RDA/DRP/CEN/KDY/KAD/11 Tiasa Construction (Pvt)… 2026-03-25 2026-09-23
22%
Update

RDA/DRP/CEN/KDY/KAD/11

Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage…

Tiasa Construction (Pvt) Ltd

Kandy Kadugannawa Awarded
Current Progress
Overall 22%
Critical Issues
Mobilization 100%
Surveying 45%
Site Clearing 100%
Base Construction 0%
Asphalt 0%
Structure Construction 10%
Drainage Construction 10%