Dashboard
Physical Progress
Physical Progress
2026-08-11
6
Awarded Projects
4 / 6
In Progress
9.7%
Avg Progress
0
Overdue
| Contract No. | Contractor | Commencement Date | Completion Date | Overall Progress | Action |
|---|---|---|---|---|---|
| RDA/DRP/CEN/KDY/KUN/20 | Samindra Construction | — | — |
0%
|
Update |
| RDA/DRP/CEN/KDY/KUN/21 | Jayasinghe Construction … | 2026-04-30 | 2026-10-28 |
5%
|
Update |
| RDA/DRP/CEN/KDY/KUN/22 | SD Civil Construction (P… | 2026-03-25 | 2026-09-23 |
35%
|
Update |
| RDA/DRP/CEN/KDY/KUN/25 | S N O Builders (Pvt) Ltd | 2026-07-06 | 2026-11-01 |
10%
|
Update |
| RDA/DRP/CEN/KDY/KUN/27 | Gihan Enterpriese | 2026-06-30 | 2026-10-27 |
0%
|
Update |
| RDA/DRP/CEN/KDY/KUN/29 | S N O Builders (Pvt) Ltd | 2026-07-06 | 2027-01-03 |
8%
|
Update |
RDA/DRP/CEN/KDY/KUN/20
RDA/DRP/CEN/KDY/KUN/21
RDA/DRP/CEN/KDY/KUN/22
RDA/DRP/CEN/KDY/KUN/25
RDA/DRP/CEN/KDY/KUN/27
RDA/DRP/CEN/KDY/KUN/29
RDA/DRP/CEN/KDY/KUN/20
Madolkelle - Kabaragala - Kandenuwara Road 5/4 and 8/1
Samindra Construction
Kandy
Kundasale
Awarded
Current Progress
Overall
0%
Critical Issues
—
Mobilization
0%
Surveying
0%
Site Clearing
0%
Base Construction
0%
Asphalt
0%
Structure Construction
0%
Drainage Construction
0%
Edit Progress
RDA/DRP/CEN/KDY/KUN/21
Pitiyegedara-Waththegama-Iriyagasthenna Road (B369)
Jayasinghe Construction (Pvt) Ltd.
Kandy
Kundasale
Awarded
Current Progress
Overall
5%
Critical Issues
In the process of Termination
Mobilization
0%
Surveying
0%
Site Clearing
0%
Base Construction
0%
Asphalt
0%
Structure Construction
0%
Drainage Construction
0%
Edit Progress
RDA/DRP/CEN/KDY/KUN/22
Weraganthota-Randenigala Road (B474)
SD Civil Construction (Pvt) Ltd
Kandy
Kundasale
Awarded
Current Progress
Overall
35%
Critical Issues
—
Mobilization
100%
Surveying
100%
Site Clearing
100%
Base Construction
0%
Asphalt
0%
Structure Construction
28%
Drainage Construction
0%
Edit Progress
RDA/DRP/CEN/KDY/KUN/25
Katugastota - Madawala - Bamberella Road
S N O Builders (Pvt) Ltd
Kandy
Kundasale
Awarded
Current Progress
Overall
10%
Critical Issues
NOT YET MOBILIZED
Mobilization
0%
Surveying
0%
Site Clearing
0%
Base Construction
0%
Asphalt
0%
Structure Construction
0%
Drainage Construction
0%
Edit Progress
RDA/DRP/CEN/KDY/KUN/27
Kandy - Jaffna Road
Gihan Enterpriese
Kandy
Kundasale
Awarded
Current Progress
Overall
0%
Critical Issues
NOT YET MOBILIZED
Mobilization
0%
Surveying
0%
Site Clearing
0%
Base Construction
0%
Asphalt
0%
Structure Construction
0%
Drainage Construction
0%
Edit Progress
RDA/DRP/CEN/KDY/KUN/29
Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) A026 and Moragahamu…
S N O Builders (Pvt) Ltd
Kandy
Kundasale
Awarded
Current Progress
Overall
8%
Critical Issues
—
Mobilization
0%
Surveying
0%
Site Clearing
0%
Base Construction
0%
Asphalt
0%
Structure Construction
0%
Drainage Construction
0%