Dashboard
Physical Progress
Physical Progress
2026-08-11
3
Awarded Projects
3 / 3
In Progress
41.0%
Avg Progress
1
Overdue
| Contract No. | Contractor | Commencement Date | Completion Date | Overall Progress | Action |
|---|---|---|---|---|---|
| RDA/DRP/CEN/MTL/MTL/32 | Lahiru Construction and … | 2026-05-02 | 2026-10-30 |
55%
|
Update |
| RDA/DRP/CEN/MTL/MTL/33 | Jayasinghe Contractors (… | 2026-05-02 | 2026-07-31 |
18%
|
Update |
| RDA/DRP/CEN/MTL/MTL/35 | Kanwel Constructions & C… | 2026-05-02 | 2026-10-30 |
50%
|
Update |
RDA/DRP/CEN/MTL/MTL/32
Kandy Jaffna Road A 009 (17+710 - 46+450), Thalgodapitiya Yatawatta Dombawela ro…
Lahiru Construction and Consultants (Pvt) Ltd
Matale
Matale
Awarded
Current Progress
Overall
55%
Critical Issues
—
Mobilization
100%
Surveying
70%
Site Clearing
50%
Base Construction
0%
Asphalt
0%
Structure Construction
30%
Drainage Construction
50%
Edit Progress
RDA/DRP/CEN/MTL/MTL/33
Wattegama Matale Road B 462,Approch road to Ukuwela Railway station B 027
Jayasinghe Contractors (Pvt) Ltd
Matale
Matale
Awarded
Current Progress
Overall
18%
Critical Issues
In the process of Termination
Mobilization
0%
Surveying
0%
Site Clearing
0%
Base Construction
0%
Asphalt
0%
Structure Construction
0%
Drainage Construction
0%
Edit Progress
RDA/DRP/CEN/MTL/MTL/35
Rattota Gammaduwa Road B 392
Kanwel Constructions & Civil Engineering (Pvt) Ltd
Matale
Matale
Awarded
Current Progress
Overall
50%
Critical Issues
—
Mobilization
100%
Surveying
100%
Site Clearing
100%
Base Construction
0%
Asphalt
0%
Structure Construction
15%
Drainage Construction
27%