Physical Progress

25 Jun 2026

Physical Progress

Manage physical progress for 5 awarded projects

RDA/DRP/CEN/NUE/NUE/66

Nuwara Eliya Town Road (B331)

KSJ Construction (Pvt) Ltd

NuwaraEliya NuwaraEliya Awarded
Current Progress
Overall 35%
Critical Issues
Mobilization 100%
Surveying 100%
Site Clearing 100%
Base Construction 0%
Asphalt 0%
Structure Construction 50%
Drainage Construction 30%
Edit Progress
View Project

RDA/DRP/CEN/NUE/NUE/67

Harangala - Kalapitiya - Kumbaloluwa Road (B148)

KSJ Construction (Pvt) Ltd

NuwaraEliya NuwaraEliya Awarded
Current Progress
Overall 30%
Critical Issues
Mobilization 100%
Surveying 90%
Site Clearing 80%
Base Construction 0%
Asphalt 0%
Structure Construction 20%
Drainage Construction 30%
Edit Progress
View Project

RDA/DRP/CEN/NUE/NUE/68

Thawalanthenna Thalawakelle Road (B412)

Green Scene Construction (Pvt) Ltd

NuwaraEliya NuwaraEliya Awarded
Current Progress
Overall 10%
Critical Issues
Mobilization 100%
Surveying 50%
Site Clearing 30%
Base Construction 0%
Asphalt 0%
Structure Construction 0%
Drainage Construction 0%
Edit Progress
View Project

RDA/DRP/CEN/NUE/NUE/69

Ulapane Pussallawa Road (B431)

Southern group civil construction (Pvt) Ltd

NuwaraEliya NuwaraEliya Awarded
Current Progress
Overall 22%
Critical Issues
Mobilization 100%
Surveying 80%
Site Clearing 80%
Base Construction 0%
Asphalt 0%
Structure Construction 15%
Drainage Construction 33%
Edit Progress
View Project

RDA/DRP/CEN/NUE/NUE/86

Approch road to R'way station (Watagoda) Road

Pragathi Civil Construction

NuwaraEliya NuwaraEliya Awarded
Current Progress
Overall 0%
Critical Issues
Mobilization 0%
Surveying 0%
Site Clearing 0%
Base Construction 0%
Asphalt 0%
Structure Construction 0%
Drainage Construction 0%
Edit Progress
View Project