Physical Progress

25 Jun 2026

Physical Progress

Manage physical progress for 1 awarded projects

RDA/DRP/CEN/NUE/NUE/66

Nuwara Eliya Town Road (B331)

KSJ Construction (Pvt) Ltd

NuwaraEliya NuwaraEliya Awarded
Current Progress
Overall 35%
Critical Issues
Mobilization 100%
Surveying 100%
Site Clearing 100%
Base Construction 0%
Asphalt 0%
Structure Construction 50%
Drainage Construction 30%