Dashboard
Physical Progress
Physical Progress
2026-08-11
1
Awarded Projects
0 / 1
In Progress
0.0%
Avg Progress
0
Overdue
| Contract No. | Contractor | Commencement Date | Completion Date | Overall Progress | Action |
|---|---|---|---|---|---|
| RDA/DRP/CEN/NUE/NUE/86 | Pragathi Civil Construct… | 2026-06-12 | 2026-09-10 |
0%
|
Update |
RDA/DRP/CEN/NUE/NUE/86
Approch road to R'way station (Watagoda) Road
Pragathi Civil Construction
NuwaraEliya
NuwaraEliya
Awarded
Current Progress
Overall
0%
Critical Issues
—
Mobilization
0%
Surveying
0%
Site Clearing
0%
Base Construction
0%
Asphalt
0%
Structure Construction
0%
Drainage Construction
0%