DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 18 awarded projects

2026-11-05
02:27:13Live2026-11-05
0 / 18Advance Pendingpending advance projects / total projects
0 / 18IPC Pendingpending IPC projects / total projects
0 / 18Advance Paidadvance paid projects / total projects
0 / 18IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Badulla · District

579Projects23,829.3Contract Mn
Badulla 18 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn138.524.163% of contract14.4——————0.0%0.0%
Tender Below 50Mn11176.2125.671% of contract50.7——————27.3%0.0%
DL Stage 014139.7102.874% of contract36.8——————100.0%0.0%
DL Stage 02226.329.3111% of contract-3.0——————0.0%0.0%
DL Stage 0300.0——————————
DL Stage 0400.0——————————
PIU00.0——————————
Badulla18380.7281.874% of contract98.9000.0000.038.9%0.0%
Tender Above 50Mn1 project38.5Mn
63% paid24.1 Mn
Pending14.4Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn11 projects176.2Mn
71% paid125.6 Mn
Pending50.7Mn
Planned Fin27.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 014 projects139.7Mn
74% paid102.8 Mn
Pending36.8Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 022 projects26.3Mn
111% paid29.3 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Badulla18 projects380.7Mn
74% paid281.8 Mn
Pending98.9Mn
Planned Fin38.9%
Actual Fin0.0%

Avg Physical Progress per Province · Badulla

Graphs reflect current view:18 awarded · Badulla
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 218 projects (filtered from 579)

71–80/218 (filtered from 579)
ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
71—
Development of the road from Punewa Junction to Kudahalmillewa Lake
Priyantha Civil Engineering
28,506,545.00————————————
72—
Development of the road from near Ikirigollawa Muslim Maha Vidyalaya to Ratmalga…
WGL Holdings
10,767,548.00————————————
73—
From Makicchawa Junction to Temple (to Kulumiwakada Junction)
Priyantha Civil Engineering
29,006,146.80————————————
74RR/RDA/21/25/03/NCP/POL
Mahasenpura pradeepika kadaya asala sita Katukeliyawa dakwa margaya Carpart kire…
Nadun Construction (Pvt) Ltd
33,480,137.33————————————
75RR/RDA/21/25/17/NCP/POL
Development of the road from Kaduruwela Muslim Kolaniya road to Pachcha Palliya
Central Engineering Services Pvt Ltd. (C…
53,880,000.00————————————
76RR/RDA/21/25/17/NCP/POL
Development of 1 canal Road from Kadurwela Muslim Kolaniya Road to Parakum Mawat…
Nadun Construction (Pvt) Ltd
54,640,000.00————————————
77RR/RDA/18/25/01/NWP/KRG
Development of Egodagama Talakolawewa road
Sri Ram Constructions
98,323,766.14————————————
78RR/RDA/18/25/04/NWP/KRG
The road from Hunugallewa road junction to Madadenigama Hunugallewa Mahamaruwa B…
Shanho Enterprises Pvt Ltd.
59,066,766.74————————————
79RR/RDA/18/25/07/NWP/KRG
Road from Moragolla Junction to Nabadewa Girilla Carpet Road via Kirinda
Jayasinghe Constructions (Pvt) Ltd.
59,247,280.29————————————
80RR/RDA/18/25/09/NWP/KRG
Paving the road from Pahala Galapitiyagama to Tharanagolla Sports Ground
Senerath Engineering (pvt) Ltd
70,405,428.60————————————
Total8,978,398,226.97——————————
—Mn
0%
—Mn
0%
Showing 71–80 of 218 projects · page 8/22