DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 37 awarded projects

2026-11-04
18:55:49Live2026-11-04
0 / 37Advance Pendingpending advance projects / total projects
0 / 37IPC Pendingpending IPC projects / total projects
0 / 37Advance Paidadvance paid projects / total projects
0 / 37IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Kandy · District

579Projects23,829.3Contract Mn
Kandy 37 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn7515.057.811% of contract457.2——————99.5%0.0%
Tender Below 50Mn20454.4162.036% of contract292.4——————80.0%0.0%
DL Stage 014110.389.381% of contract21.0——————100.0%0.0%
DL Stage 024140.386.962% of contract53.4——————100.0%0.0%
DL Stage 03224.318.074% of contract6.3——————100.0%0.0%
DL Stage 0400.0——————————
PIU00.0——————————
Kandy371,244.4414.133% of contract830.3000.0000.089.1%0.0%
Tender Above 50Mn7 projects515.0Mn
11% paid57.8 Mn
Pending457.2Mn
Planned Fin99.5%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn20 projects454.4Mn
36% paid162.0 Mn
Pending292.4Mn
Planned Fin80.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 014 projects110.3Mn
81% paid89.3 Mn
Pending21.0Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 024 projects140.3Mn
62% paid86.9 Mn
Pending53.4Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 032 projects24.3Mn
74% paid18.0 Mn
Pending6.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Kandy37 projects1,244.4Mn
33% paid414.1 Mn
Pending830.3Mn
Planned Fin89.1%
Actual Fin0.0%

Avg Physical Progress per Province · Kandy

Graphs reflect current view:37 awarded · Kandy
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

521–530/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
521RR/RDA/07/25/07
Hapugala batuwanthuda Margaya Pivisume sita Roswudwatta Margaye Kelawara Dakwa M…
—
27,520,890.73————————————
522RR/RDA/07/25/16
Mahabodhiwatta sita Pongiliya haraha Vitahna Gedera Ela Dakwa Margaya Ketapathal…
—
30,597,079.78————————————
523RR/RDA/25/08/07
Ovitigamuwa Alahenpita margaya Sanwardanaya Kirima (RDA yatathe Idikirima Arambh…
—
29,034,089.99————————————
524RR/RDA/25/08/01
Kajjuhena Margaya Sanwardanaya Kirima (Kajjuhena Handiya Sita Alikavila Budu Mad…
—
78,061,393.44————————————
525RR/RDA/08/25/04
Vigamuwa Pattiyapola Road from Vigamuwa School
—
74,802,039.66————————————
526RR/RDA/09/25/01
Karametiya Road
—
74,446,690.12————————————
527RR/RDA/07/25/03
Wackwella Palama asala sita aranbe handiya dakwa Margaya
—
26,781,909.97————————————
528RR/RDA/07/25/04
Galwehera C.P. the Silva Mawatha Carpet kirima
—
30,571,235.08————————————
529RR/RDA/07/25/18
Agaliya Uthura Tranformaraya Sita Savanna Wella desata Margaya Interlock Kirima
—
27,525,465.50————————————
530RR/RDA/25/08/06
Samarasinghe Mawathw Ithiri Kotasa Sanwardanaya Kirima
—
17,005,961.71————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 521–530 of 579 projects · page 53/58