DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 20 awarded projects

2026-11-05
03:22:36Live2026-11-05
0 / 20Advance Pendingpending advance projects / total projects
0 / 20IPC Pendingpending IPC projects / total projects
0 / 20Advance Paidadvance paid projects / total projects
0 / 20IPCs PaidIPC paid projects / total projects
544.8 Mn

544.76 Mn

Total Contract

0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

0%

0%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

51.5%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Matara · District

579Projects23,829.3Contract Mn
Matara 20 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn2216.4—216.4——————0.0%0.0%
Tender Below 50Mn11140.0117.184% of contract22.9——————100.0%0.0%
DL Stage 012107.162.658% of contract44.5——————100.0%0.0%
DL Stage 02226.421.883% of contract4.6——————100.0%0.0%
DL Stage 0317.23.650% of contract3.6——————100.0%0.0%
DL Stage 04247.624.551% of contract23.1——————0.0%0.0%
PIU00.0——————————
Matara20544.8229.642% of contract315.2000.0000.080.0%0.0%
Tender Above 50Mn2 projects216.4Mn
0% paid0.0 Mn
Pending216.4Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn11 projects140.0Mn
84% paid117.1 Mn
Pending22.9Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 012 projects107.1Mn
58% paid62.6 Mn
Pending44.5Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 022 projects26.4Mn
83% paid21.8 Mn
Pending4.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 project7.2Mn
50% paid3.6 Mn
Pending3.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 042 projects47.6Mn
51% paid24.5 Mn
Pending23.1Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Matara20 projects544.8Mn
42% paid229.6 Mn
Pending315.2Mn
Planned Fin80.0%
Actual Fin0.0%

Avg Physical Progress per Province · Matara

Graphs reflect current view:20 awarded · Matara
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 218 projects (filtered from 579)

141–150/218 (filtered from 579)
ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
141RR/RDA/13/25/03/NP/MUL
Navatkadu Road
TMC Constructions
50,363,687.00————————————
142RR/RDA/13/25/06/NP/MUL
Pandaravanniyan Silaiyadi Road
Sun Constructions (Pvt) Ltd.
83,700,000.00————————————
143RR/RDA/13/25/07/NP/MUL
Kanagarayankulam District Boundary Road (Old Kandy road)
Sun Constructions (Pvt) Ltd.
159,972,500.00————————————
144RR/RDA/13/25/08/NP/MUL
Kumulamunai Akkarayan road
Nimna Holdings (Pvt) Ltd
148,861,042.00————————————
145RR/RDA/13/25/10/NP/MUL
Pandiyankulam Neddankandal Road
Nimna Holdings (Pvt) Ltd
144,696,282.50————————————
146RR/RDA/13/25/11/NP/MUL
Ethawetuvuwewa to Sampathnuwara
Nimna Holdings (Pvt) Ltd
110,422,944.50————————————
147RR/RDA/11/25/01/NP/MNR
Mahilankulam Pallamadhu road
George Steuart Engineering (Pvt)Ltd
189,602,588.30————————————
148RR/RDA/11/25/02/NP/MNR
Piramanayankulam Parappukadanthan road
George Steuart Engineering (Pvt)Ltd
169,538,631.82————————————
149RR/RDA/11/25/04/NP/MNR
Tharavankottai to Keeri Main Road
VN Construction JV
146,489,579.50————————————
150RR/RDA/11/25/07/NP/MNR
Avithappar Panimayam Internal Road with Culvert - Pesalai
VN Construction JV
—————————————
Total8,978,398,226.97——————————
—Mn
0%
—Mn
0%
Showing 141–150 of 218 projects · page 15/22