DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 20 awarded projects

2026-11-05
02:59:08Live2026-11-05
0 / 20Advance Pendingpending advance projects / total projects
0 / 20IPC Pendingpending IPC projects / total projects
0 / 20Advance Paidadvance paid projects / total projects
0 / 20IPCs PaidIPC paid projects / total projects
544.8 Mn

544.76 Mn

Total Contract

0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

0%

0%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

51.5%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Matara · District

579Projects23,829.3Contract Mn
Matara 20 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn2216.4—216.4——————0.0%0.0%
Tender Below 50Mn11140.0117.184% of contract22.9——————100.0%0.0%
DL Stage 012107.162.658% of contract44.5——————100.0%0.0%
DL Stage 02226.421.883% of contract4.6——————100.0%0.0%
DL Stage 0317.23.650% of contract3.6——————100.0%0.0%
DL Stage 04247.624.551% of contract23.1——————0.0%0.0%
PIU00.0——————————
Matara20544.8229.642% of contract315.2000.0000.080.0%0.0%
Tender Above 50Mn2 projects216.4Mn
0% paid0.0 Mn
Pending216.4Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn11 projects140.0Mn
84% paid117.1 Mn
Pending22.9Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 012 projects107.1Mn
58% paid62.6 Mn
Pending44.5Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 022 projects26.4Mn
83% paid21.8 Mn
Pending4.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 project7.2Mn
50% paid3.6 Mn
Pending3.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 042 projects47.6Mn
51% paid24.5 Mn
Pending23.1Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Matara20 projects544.8Mn
42% paid229.6 Mn
Pending315.2Mn
Planned Fin80.0%
Actual Fin0.0%

Avg Physical Progress per Province · Matara

Graphs reflect current view:20 awarded · Matara
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

141–150/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
141—
From Makicchawa Junction to Temple (to Kulumiwakada Junction)
Priyantha Civil Engineering
29,006,146.80————————————
142—
Paddy Depot Road near Padaviya Divisional Secretariat to the entrance road to th…
Pathiraja Construction
37,594,579.00————————————
143—
road from near Mekichchawa Temple to Gammehegewewa.
Kumari Konthrathkaruwo
39,727,992.71————————————
144—
Maradankulam Weerakele Temple Road.
Lisal Construction
34,408,719.40————————————
145RR/RDA/21/25/03/NCP/POL
Mahasenpura pradeepika kadaya asala sita Katukeliyawa dakwa margaya Carpart kire…
Nadun Construction (Pvt) Ltd
33,480,137.33————————————
146RR/RDA/21/25/04/NCP/POL
10th Canal Lake Road
Nadun Construction (Pvt) Ltd
18,877,127.00————————————
147RR/RDA/21/25/17/NCP/POL
Development of the road from Kaduruwela Muslim Kolaniya road to Pachcha Palliya
Central Engineering Services Pvt Ltd. (C…
53,880,000.00————————————
148RR/RDA/21/25/17/NCP/POL
Development of 1 canal Road from Kadurwela Muslim Kolaniya Road to Parakum Mawat…
Nadun Construction (Pvt) Ltd
54,640,000.00————————————
149—
Development of the road from near the Pimburatthewa Mahaweli Resort to the Arala…
Sawsiri Construction
59,570,000.00————————————
150—
Development of the road from near the railway on the entrance road to the house …
Nathan's Construction
73,470,000.00————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 141–150 of 579 projects · page 15/58