DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 27 awarded projects

2026-11-04
19:07:43Live2026-11-04
0 / 27Advance Pendingpending advance projects / total projects
0 / 27IPC Pendingpending IPC projects / total projects
0 / 27Advance Paidadvance paid projects / total projects
0 / 27IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Ratnapura · District

579Projects23,829.3Contract Mn
Ratnapura 27 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn3225.622.110% of contract203.5——————66.7%0.0%
Tender Below 50Mn14279.282.329% of contract196.9——————95.7%0.0%
DL Stage 013113.5104.092% of contract9.5——————100.0%0.0%
DL Stage 02256.855.598% of contract1.3——————100.0%0.0%
DL Stage 03127.813.950% of contract13.9——————100.0%0.0%
DL Stage 044335.055.216% of contract279.9——————100.0%0.0%
PIU00.0——————————
Ratnapura271,037.9332.932% of contract705.0000.0000.094.1%0.0%
Tender Above 50Mn3 projects225.6Mn
10% paid22.1 Mn
Pending203.5Mn
Planned Fin66.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn14 projects279.2Mn
29% paid82.3 Mn
Pending196.9Mn
Planned Fin95.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 013 projects113.5Mn
92% paid104.0 Mn
Pending9.5Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 022 projects56.8Mn
98% paid55.5 Mn
Pending1.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 project27.8Mn
50% paid13.9 Mn
Pending13.9Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 044 projects335.0Mn
16% paid55.2 Mn
Pending279.9Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Ratnapura27 projects1,037.9Mn
32% paid332.9 Mn
Pending705.0Mn
Planned Fin94.1%
Actual Fin0.0%

Avg Physical Progress per Province · Ratnapura

Graphs reflect current view:27 awarded · Ratnapura
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 291 projects (filtered from 579)

31–40/291 (filtered from 579)
ActiveProgress 100–100%
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
31RR/RDA/STA II/16/25/04/AKK/A…
Lahugala Hulannuge Roundabout road
Zaka Engineering Consultancy
26,597,958.20————————————
32RR/RDA/16/25/10KM/06/AKK/AKK
Hulannuge School Road
Gama Construction & Consultant pvt Ltd
11,406,166.73————————————
33RR/RDA/16/25/10KM/09/AKK/AKK
Road behind Necode Institute (Navatkadu Akkarapattu)
SMA Careem Engineering Consultancy Servi…
15,228,903.25————————————
34RR/RDA/15/25/01/EP/BTC
Concreting to Vipulananthar road
SSK Construction
29,074,090.89————————————
35RR/RDA/15/25/07/EP/BTC
Concreting to Thakwa masjith Cross Road
Nazeeha Hardware and Construction
22,206,567.30————————————
36RR/RDA/17/25/01/EP/TRN
Pillayar Road Renovation
Rina Construction
23,425,921.56————————————
37RR/RDA/17/25/02/EP/TRN
Kathirkamathambi Road
Fareed
28,809,738.00————————————
38RR/RDA/17/25/03/EP/TRN
Hospital Road
Pragash Construction
18,557,253.77————————————
39RR/RDA/17/25/07/EP/TRN
Kanthamalawa Main Road
SSK Construction
9,161,570.00————————————
40RR/RDA/17/25/10/EP/TRN
From Medagama temple to Peramaduwa
Soyuru Sampath Construction & Suppliers
24,197,635.00————————————
Total8,230,991,569.86——————————
—Mn
0%
—Mn
0%
Showing 31–40 of 291 projects · page 4/30