DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 6 awarded projects

2026-11-04
22:09:57Live2026-11-04
0 / 6Advance Pendingpending advance projects / total projects
0 / 6IPC Pendingpending IPC projects / total projects
0 / 6Advance Paidadvance paid projects / total projects
0 / 6IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · EE: Ampara · EE Office

567Projects20,718.2Contract Mn
Ampara 6 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn1222.2105.347% of contract116.9——————100.0%0.0%
Tender Below 50Mn453.59.017% of contract44.6——————100.0%0.0%
DL Stage 011171.7100.158% of contract71.7——————0.0%0.0%
DL Stage 0200.0——————————
DL Stage 0300.0——————————
DL Stage 0400.0——————————
Ampara6447.4214.348% of contract233.1000.0000.083.3%0.0%
Tender Above 50Mn1 project222.2Mn
47% paid105.3 Mn
Pending116.9Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn4 projects53.5Mn
17% paid9.0 Mn
Pending44.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project171.7Mn
58% paid100.1 Mn
Pending71.7Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 020 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Ampara6 projects447.4Mn
48% paid214.3 Mn
Pending233.1Mn
Planned Fin83.3%
Actual Fin0.0%

Avg Physical Progress per Province · EE: Ampara

Project-wise Financials · EE: Ampara (579 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Ampara (Mn · incl. VAT)

Scroll horizontally — 579 projects

Ampara Division · EE: Ampara (Mn · incl. VAT)

Ampara District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:6 awarded · EE: Ampara
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

501–510/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
501RR/RDA/13/25/05
Suthanthirapuram Main Road Package 2
—
63,852,534.37————————————
502RR/RDA/12/25/11
Madeenanagar road
—
21,394,474.49————————————
503RR/RDA/13/25/02
Kokkilai Estuary fishing village Road
—
26,445,698.08————————————
504RR/RDA/10/25/23
Oorany Kudiyetta thidda Veethy
—
12,148,965.86————————————
505RR/RDA/25/24/07
Godawela Wela Middle Road (Const. side walls)
—
21,801,991.89————————————
506RR/RDA/25/24/15
D03 Road Near the Yaka Poll
—
52,683,572.48————————————
507RR/RDA/25/24/08
From Mr.Ranjth's House to Mr.Premasiri's House in Maduwanwela Janapadaya 2nd Lan…
—
39,030,233.29————————————
508RR/RDA/25/25/16
Ma dola Jansalu Mawatha Rathnapuara Colombo Road to Welangalla Maha ela Bridge
—
40,604,043.84————————————
509RR/RDA/25/25/17
Na gahamula Junction to 28 Janapadaya Road
—
30,370,502.56————————————
510RR/RDA/25/24/12
Siyabalagahayata Junction to Blue Mountain Housing Complex Road
—
23,571,917.19————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 501–510 of 579 projects · page 51/58