DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 0 awarded projects

2026-11-04
19:13:00Live2026-11-04
0 / 0Advance Pendingpending advance projects / total projects
0 / 0IPC Pendingpending IPC projects / total projects
0 / 0Advance Paidadvance paid projects / total projects
0 / 0IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Total Contract

0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

0%

0%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

0%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Northern Province · EE: Batticaloa · EE Office

567Projects20,718.2Contract Mn
Batticaloa 17 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn00.0——————————
Tender Below 50Mn15339.568.520% of contract271.0——————46.7%0.0%
DL Stage 01132.432.199% of contract0.3——————100.0%0.0%
DL Stage 02133.924.572% of contract9.4——————100.0%0.0%
DL Stage 0300.0——————————
DL Stage 0400.0——————————
Batticaloa17405.9125.131% of contract280.8000.0000.053.0%0.0%
Tender Above 50Mn0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn15 projects339.5Mn
20% paid68.5 Mn
Pending271.0Mn
Planned Fin46.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project32.4Mn
99% paid32.1 Mn
Pending0.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project33.9Mn
72% paid24.5 Mn
Pending9.4Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Batticaloa17 projects405.9Mn
31% paid125.1 Mn
Pending280.8Mn
Planned Fin53.0%
Actual Fin0.0%

Avg Physical Progress per Province · Northern Province · EE: Batticaloa

No province data available

Awarded projects will appear here

Project-wise Financials · Northern Province · EE: Batticaloa (218 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · Northern Province · EE: Batticaloa (Mn · incl. VAT)

Scroll horizontally — 218 projects

Batticaloa Division · Northern Province · EE: Batticaloa (Mn · incl. VAT)

District District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:0 awarded · Northern Province · EE: Batticaloa
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 218 projects (filtered from 579)

1–10/218 (filtered from 579)
ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
1RR/RDA/04/25/13/CP/KY
Gonaala Pasala Asala Sita Kubukkadura Athuru Margayak Wana Gurumada Margaya
Dharshana Construction
35,195,820.00————————————
2RR/RDA/04/25/19/CP/KY
Mulgama viduhala Asala sita lewalan dakwa
The Wise Lanka Construction Company (Pvt…
25,917,512.50————————————
3RR/RDA/04/25/20/CP/KY
Carpeting road Ratemulla to Wendesiwaththa End
Wiscon (Pvt) Ltd
36,995,817.10————————————
4RR/RDA/04/25/21/CP/KY
Galaha group sita finas kotasa Pahalagama-Ihalagama haraha nawa rohala dakwa Mar…
UGD Constructions
22,711,029.00————————————
5RR/RDA/04/25/25/CP/KY
Delgasthenna Road
NAGMA ENGINEERING (PVT) LTD
56,035,922.24————————————
6RR/RDA/04/25/28/CP/KY
Dehideniya sita Hedeniya dakwa Margaya
Senerath Engineering (pvt) Ltd
38,495,776.00————————————
7RR/RDA/04/25/31(1)/CP/KY
Paththunupitiya School road to Gampola Road through Pallegama Anguruwala
Central Engineering Services Pvt Ltd. (C…
50,476,865.28————————————
8RR/RDA/04/25/41/CP/KY
Karyala handiya pahala margya concrete kirima
UGD Constructions
22,047,564.00————————————
9RR/RDA/04/25/52/CP/KY
Bokalawela Road from Hapugoda Junction to Ranawana (Drinage System Development a…
Senerath Engineering (pvt) Ltd
50,478,905.00————————————
10RR/RDA/04/25/53/CP/KY
Road from Amuvandeniya to Magurudeniya (development of the drainage and carpetin…
Tiasa Construction (Pvt) Ltd
29,850,460.20————————————
Total8,978,398,226.97——————————
—Mn
0%
—Mn
0%
Showing 1–10 of 218 projects · page 1/22