DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 18 awarded projects

2026-11-04
13:25:25Live2026-11-04
0 / 18Advance Pendingpending advance projects / total projects
0 / 18IPC Pendingpending IPC projects / total projects
0 / 18Advance Paidadvance paid projects / total projects
0 / 18IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · EE: Galle · EE Office

567Projects20,718.2Contract Mn
Galle 18 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn292.717.118% of contract75.6——————50.0%0.0%
Tender Below 50Mn10253.087.835% of contract165.2——————79.7%0.0%
DL Stage 01127.517.864% of contract9.8——————100.0%0.0%
DL Stage 02257.438.367% of contract19.1——————100.0%0.0%
DL Stage 03121.212.961% of contract8.3——————100.0%0.0%
DL Stage 04298.170.071% of contract28.1——————50.0%0.0%
Galle18549.8243.944% of contract306.0000.0000.077.6%0.0%
Tender Above 50Mn2 projects92.7Mn
18% paid17.1 Mn
Pending75.6Mn
Planned Fin50.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn10 projects253.0Mn
35% paid87.8 Mn
Pending165.2Mn
Planned Fin79.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project27.5Mn
64% paid17.8 Mn
Pending9.8Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 022 projects57.4Mn
67% paid38.3 Mn
Pending19.1Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 project21.2Mn
61% paid12.9 Mn
Pending8.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 042 projects98.1Mn
71% paid70.0 Mn
Pending28.1Mn
Planned Fin50.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Galle18 projects549.8Mn
44% paid243.9 Mn
Pending306.0Mn
Planned Fin77.6%
Actual Fin0.0%

Avg Physical Progress per Province · EE: Galle

Project-wise Financials · EE: Galle (291 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Galle (Mn · incl. VAT)

Scroll horizontally — 291 projects

Galle Division · EE: Galle (Mn · incl. VAT)

Galle District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:18 awarded · EE: Galle
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 291 projects (filtered from 579)

21–30/291 (filtered from 579)
ActiveProgress 100–100%
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
21RR/RDA/05/25/19/CP/MTL
Katudeniya bahukarya godanagilla asala Hettiyawatta dakwa margaya
Ajith Construction
13,129,506.50————————————
22RR/RDA/05/25/20/CP/MTL
Harispattuwa margaya arambaka mansandiye sita Thusitha maranadara godanagilla da…
Ajith Construction
15,584,937.50————————————
23RR/RDA/05/25/22/CP/MTL
Sigirimulla sita Mailetthewa Aluthyaya dakwa margaya
Asiri Contractor and Designers
33,057,264.90————————————
24RR/RDA/05/25/24/CP/MTL
Pahala Hombawa palama dakwa Daduwagolla kanaththa langa sita
Ajith Construction
35,817,952.50————————————
25RR/RDA/05/25/27/CP/MTL
Welemulla sita Kandewaththa
Ajith Construction
23,207,525.00————————————
26RR/RDA/05/25/29/CP/MTL
Pitawala handiye sita pitawala desata
Lahiru Construction & Consultants (PVT) …
37,136,372.90————————————
27RR/RDA/06/25/37/CP/NE
Gewal wissa handiye sita Bogalkanda dakwa Margaye asiru sthan
Ajith Construction
28,282,100.00————————————
28RR/RDA/16/25/04/AKK/AMP
Pokunugama near Mr. Dinesh Tharaga House to Road (From Pokunugama Pre School to …
Harischandra Idikirim
6,435,000.00————————————
29RR/RDA/16/25/01/AKK/AMP
Samanalathenna- Road from House No.63 To the Monastery Muwagammana -From First L…
Vithu Construction
21,336,681.87————————————
30RR/RDA/STA II/16/25/02/AKK/A…
Concreting entrance road with culvert at Dehiaththakandiya Kelegama
Vithu Construction
30,737,790.60————————————
Total8,230,991,569.86——————————
—Mn
0%
—Mn
0%
Showing 21–30 of 291 projects · page 3/30