DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 11 awarded projects

2026-11-04
12:49:06Live2026-11-04
0 / 11Advance Pendingpending advance projects / total projects
0 / 11IPC Pendingpending IPC projects / total projects
0 / 11Advance Paidadvance paid projects / total projects
0 / 11IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · EE: Medawachchiya · EE Office

567Projects20,718.2Contract Mn
Medawachchiya 11 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn00.0——————————
Tender Below 50Mn7188.80.10% of contract188.7——————0.0%0.0%
DL Stage 01121.223.1109% of contract-1.9——————100.0%0.0%
DL Stage 02136.9—36.9——————0.0%0.0%
DL Stage 03135.333.495% of contract1.9——————0.0%0.0%
DL Stage 04137.539.2105% of contract-1.7——————0.0%0.0%
Medawachchiya11319.795.830% of contract223.9000.0000.09.1%0.0%
Tender Above 50Mn0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn7 projects188.8Mn
0% paid0.1 Mn
Pending188.7Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project21.2Mn
109% paid23.1 Mn
Pending—
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project36.9Mn
0% paid0.0 Mn
Pending36.9Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 project35.3Mn
95% paid33.4 Mn
Pending1.9Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 041 project37.5Mn
105% paid39.2 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Medawachchiya11 projects319.7Mn
30% paid95.8 Mn
Pending223.9Mn
Planned Fin9.1%
Actual Fin0.0%

Avg Physical Progress per Province · EE: Medawachchiya

Project-wise Financials · EE: Medawachchiya (218 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Medawachchiya (Mn · incl. VAT)

Scroll horizontally — 218 projects

Medawachchiya Division · EE: Medawachchiya (Mn · incl. VAT)

Anuradhapura District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:11 awarded · EE: Medawachchiya
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 218 projects (filtered from 579)

201–210/218 (filtered from 579)
ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
201RR/RDA/03/25/12/WP/KTR
Concreting Batawala Road
Next Engineering Services (PVT) LTD
18,670,236.20————————————
202RR/RDA/03/25/16/WP/KTR
Development of carpeting of 1 km from Gane Aramba Road, Bogalla Junction to Ambe…
Asela Construction
27,990,360.00————————————
203—
Development of 0.8 km carpeting of Newfa Mawatha
Develco Engineering (PVT) LTD
6,972,603.95————————————
204RR/RDA/03/25/18/WP/KTR
Development of carpeting of the section (length 800 m) from near Minerithenna te…
Asela Construction
17,101,775.00————————————
205—
Carpeting and development of 500 meters of Moragahakanda watta Bodumaga Senasuna…
Develco Engineering (PVT) LTD
8,285,619.00————————————
206—
Development of from Lewis Stadium to Heladiva Malshalawa
Develco Engineering (PVT) LTD
15,591,781.10————————————
207RR/RDA/06/25/44
Carpeting of Muloya Main Road Section 2
—
42,312,390.95————————————
208RR/RDA/06/25/47
Carpeting of the road from Gatakula to Madanwala via Diaudagama, Kottala
—
28,020,844.83————————————
209RR/RDA/05/25/23
Manchanayake shed eka asala sita sampath waththa haraha Galketiyawa margaya
—
28,401,905.12————————————
210RR/RDA/05/25/28
Adawala Udagama Road
—
56,161,142.68————————————
Total8,978,398,226.97——————————
—Mn
0%
—Mn
0%
Showing 201–210 of 218 projects · page 21/22